Abstract
Purpose
This paper examines the conflict between rule-based and principle-based approaches to benefits realisation in agile projects. It proposes a principle-based framework as a more effective alternative, aligned with the iterative and adaptive nature of agile methodologies.
Design/methodology/approach
The research utilises semi-structured interviews to gather qualitative data from professionals experienced in agile projects. Causal loop diagrams are employed to illustrate the relationships between identified principles. The study identifies 12 key principles essential for agile benefits realisation, with a particular focus on visibility and consequence management.
Findings
The study finds that a principle-based approach to benefits realisation is more compatible with agile methodologies compared to a rule-based approach. The flexibility of principle-based decision-making allows for continuous adaptation and improvement, aligning with the dynamic and iterative nature of agile projects. The principles of visibility and consequence management emerge as critical factors in successfully realising benefits in an agile environment.
Research limitations/implications
The findings are based on qualitative data from a limited number of interviews, which may not be generalisable across all agile projects. Further research with a larger sample size and diverse project types is recommended to validate and refine the proposed principles.
Practical implications
Agile teams and project managers can leverage the identified principles to enhance their decision-making processes and improve benefits realisation outcomes. Adopting a principle-based approach can lead to more flexible, responsive and effective project management practices.
Social implications
By promoting more adaptive and responsive project management practices, the adoption of a principle-based approach can contribute to greater satisfaction and collaboration among project stakeholders, leading to more successful project outcomes.
Originality/value
This research contributes to the existing body of knowledge by highlighting the limitations of rule-based approaches in agile contexts and proposing a principle-based framework for benefits realisation. The identification of specific principles and their interrelationships provides a novel perspective and practical guidance for agile practitioners.
Keywords
Citation
Marnewick, C. and Marnewick, A.L. (2024), "Principle-based decision-making: realising benefits in a scaled agile environment", International Journal of Managing Projects in Business, Vol. 17 No. 8, pp. 119-139. https://doi.org/10.1108/IJMPB-07-2024-0164
Publisher
:Emerald Publishing Limited
Copyright © 2024, Carl Marnewick and Annlizé L. Marnewick
License
Published by Emerald Publishing Limited. This article is published under the Creative Commons Attribution (CC BY 4.0) licence. Anyone may reproduce, distribute, translate and create derivative works of this article (for both commercial and non-commercial purposes), subject to full attribution to the original publication and authors. The full terms of this licence may be seen at http://creativecommons.org/licences/by/4.0/legalcode
1. Introduction
Project management and benefits realisation specifically are focused on processes, rules and procedures. Adhering to processes and rules eliminates decision-making since the benefits owner should just follow the processes and rules and tick that everything was done according to the book (standards and/or best practices) (Project Management Institute, 2016; Zwikael et al., 2019). When ethics, philosophy and moral reasoning become the foundation upon which benefits realisation is built, then processes and rules no longer make sense. A principle-based approach to benefits realisation then makes more sense (Marnewick and Marnewick, 2022). Unfortunately, all literature on benefits realisation focuses on processes and rules, irrespective of the industry and type of project.
Although benefits are identified within the business case at the start of the project, they are only realised after the completion of the project (Einhorn et al., 2019). However, this is not practical when it comes to iterative (agile) projects within a scaled agile environment. When agile is the preferred project management approach, then frequent solutions or minimum viable products are delivered, which makes process-driven benefits realisation irrelevant. Due to the success and popularity of agile, scaled agile was introduced. Agile principles and practices are extended across multiple teams or an entire organisation to improve collaboration, alignment and delivery of value at scale. There are different frameworks for scaling agile including Rage, Spotify, Nexus, Scrum@Scale, Scaled Agile Framework (SAFe), Large-Scale Scrum (LeSS) and Disciplined Agile Delivery (DAD) (Alqudah and Razali, 2016; Turetken et al., 2017). The most adopted frameworks are SAFe and Scrum@Scale (Khoza and Marnewick, 2021; VersionOne Inc., 2020).
Benefits realisation has been a topic of research for a long time, with the first articles appearing as early as 1996 (Kransdorff, 1996). Since then, research has focused on the processes (Ashurst, 2011; Bradley, 2010), who is responsible for benefits realisation (Romero-Torres, 2021; Zwikael et al., 2019), as well as benefits realisation and project success (Doherty et al., 2012; Serra and Kunc, 2015; ul Musawir et al., 2017). This research was built on the premise that a predictive or waterfall approach is followed. A predictive approach is very much process or rules driven, with limited focus on guiding principles. Also, limited or no research has been conducted on how benefits realisation should be done when the project management approach is either agile (for instance scrum) or scaled agile (for instance SAFe).
This paper addresses two identified gaps. The first is the misalignment between agile, which is principle driven (Dingsøyr et al., 2012), and benefits realisation, which is process driven. Processes or rules are important but do not improve the success of benefits realisation. The argument is that a different approach (principle-based) is required to manage benefits in a scaled agile environment. Ethical reasoning and decision theory are used to motivate this transition. This is in line with the Project Management Institute’s latest release of the PMBoK® Guide (Project Management Institute, 2021), in which the focus is on principles and not processes. The second gap that this article addresses is the identification of certain principles that can form the foundation of benefits realisation in a scaled environment.
Based on the identified gaps, the following research questions were formulated:
- (1)
How does decision-making influence a principle-based approach to agile benefits realisation?
- (2)
What principles drive decision-making regarding benefits realisation in a scaled agile environment?
The first section of this article consists of the literature review. The literature review focuses on ethical and decision theories to motivate principle-based agile benefits realisation. This is followed by the research methodology section in which the rationale for using interviews and causal loops is explained. The analysis of the interviews forms the fourth section. The article concludes with a discussion section.
2. Literature review
To understand the way we make decisions and how these decisions influence benefits realisation, we must understand the philosophies around decision-making and what influences these decisions. The foundation of decision-making is based on ethical theories such as deontology and utilitarianism. These two theories suggest that responses to moral dilemmas are guided by two moral principles. The principle of deontology states that the morality of an action depends on the intrinsic nature of the action (e.g. harming others is wrong, regardless of its consequences). Within deontological ethics, obligations are of prime importance (i.e. the outcome may not justify the means). The principle of utilitarianism implies that the morality of an action is determined by its consequences (e.g. harming others is acceptable if it increases the well-being of a greater number of people). In utilitarian ethics, outcomes justify the means.
2.1 Ethical theories
Deontology and utilitarianism are two distinct ethical theories that guide decision-making in various fields, including project management. These ethical theories offer different approaches to assess the moral implications of actions and to make ethical choices. In the context of project management, understanding the differences between deontology and utilitarianism is crucial for project managers to navigate complex ethical dilemmas.
The first ethical theory that underpins decision-making is deontology, also referred to as Kantian ethics (White, 2009). It focuses on which choices are morally required, forbidden or permitted. In other words, deontology guides and assesses choices of what can be done. It measures intention and internal logic (Waters, 2020). This contrasts with those choices that guide and assess what kind of person we are and should be. Decisions must be made that are always applicable within all situations. In essence, deontology is a duty-based ethical theory that emphasises the inherent rightness or wrongness of decisions, irrespective of their consequences.
In utilitarianism, decisions are made based on the greatest amount of benefit obtained for the greatest number of individuals. Measurement is based on pleasure and pain (Waters, 2020). This is also known as consequentialism, since the outcomes determine the morality of the intervention. Decisions are made based on the greatest happiness principle, i.e. the greatest pleasure for the greatest number of people. Utilitarianism asserts that the moral worth of a decision is determined by its positive or negative impact on the well-being of all affected parties.
In answering the question of how many consequences matter based on a specific action or decision, deontology focuses on making the right decisions all the time, irrespective of the outcome or consequences. Utilitarianism focuses on the consequences of the decision. The consequences therefore influence the decision. In utilitarianism, outcomes justify the means and as such the focus is on the consequences of an action, whereas in deontology, the obligation to duty is what matters, irrespective of the outcome.
Bose (2012) maintains that ethical theories guide our ethical decision-making at a personal as well as professional level. Deontology and utilitarianism shape decision-making by providing distinct ethical frameworks. Deontology emphasises adherence to principles and duties, leading to principled and consistent decisions. Utilitarianism emphasises evaluating outcomes to maximise overall good, leading to decisions aimed at achieving the best possible consequences.
2.2 Decision-making
Project managers make decisions with the intent that this might lead to success (Harrison and Pelletier, 2000). However, decision-making is complex and dynamic, and the result is not always positive. Harrison and Pelletier (2000) define a decision as “a moment in an ongoing process of evaluating alternatives for meeting an objective, at which expectations about a particular course of action impel the decision maker to select that course of action most likely to result in attaining the objective”. A decision is typically a choice between at least two alternatives (Peterson, 2017). The aim of a decision is to maximise the desired consequences and at the same time, minimise the consequences that are deemed undesirable. Making a decision is an either/or situation (Idler and Spang, 2019), as the decision-maker must choose between two options.
Decision-making and its subsequent consequences have been with us for centuries. Keren and Wagenaar (1985) trace the roots of modern decision theory to the 17th century when French mathematicians explored optimal gambling behaviour. Since then, various decision theories have seen the light. When it comes to individual decision-making, two theories are applicable: normative and descriptive (Małecka, 2020; Peterson, 2017). Bell et al. (1988) add a third theory called prescriptive decision-making theory, which is a combination of normative and descriptive decision-making theories.
- (1)
Normative decision theory: The focus of this theory is to provide advice on how to make the best decisions. Decisions are made within a set of uncertain beliefs and a set of values. The focus is on what project members should do in theory. Decisions are evaluated based on the degree to which the decisions provide acceptable rational choice (Bell et al., 1988).
- (2)
Descriptive decision theory: This theory focuses on characterising and explaining regularities in the choices that people are making. The focus is on understanding real human decision-making behaviour (Idler and Spang, 2019) and on what project members do or did. Decisions are evaluated based on the extent to which they correspond with observed choices (Bell et al., 1988).
- (3)
Prescriptive decision theory: This theory provides procedures on how or what should be done to make the best decisions in line with normative theory. The focus is on what project members should and can do from a practical perspective and not from a theoretical perspective (normative decision theory). Evaluation is based on the ability of the decisions to assist project members in making better decisions (Bell et al., 1988).
For this article, the focus is on normative decision theory, which is associated with principles, and descriptive decision theory, which is associated with rules and processes.
Normative decision theory is built on rational decision-making. Human beings by nature are by and large rational (Keren and Wagenaar, 1985). Normative decision theory prescribes how people should behave and make choices (Małecka, 2020). A decision is perceived as a rational selection issue through deducing the logically best alternative (Peterson, 2017). Choosing the logically best alternative is dependent on consistent preferences and making decisions in accordance with these preferences (Thoma, 2021). This relates to deontology where decisions must be made that are always applicable within all situations.
Descriptive decision theory provides procedures or processes for what should be done to make the best decision when a decision should be made. The underlying concept of descriptive decision theory is expected utility theory (Cohen, 1996). The premise is to start with axioms that are basic rules that any rational individual would adhere to when they need to make a decision. Rules should be rational and determine what conduct is permissible (Ford, 2008). The decision-maker is left to determine factual issues. This contrasts with principles where the decision-maker must consider permissible conduct as well as factual issues. Rule-based or descriptive decision-making enforces strict sanctions for violating the rules or for non-compliance (Sama and Shoaf, 2005).
Decision-making features within project management literature with various authors investigating this phenomenon. The literature can be divided into two viewpoints. One viewpoint focuses on decision-making in general and the other explores decision-making through a theoretical lens. The theoretical viewpoint is then further subdivided into naturalistic and behavioural decision-making.
From a naturalistic decision-making perspective, Turner (2020) investigated the impact of governance on decision-making. He concluded that governance does not influence decision-making, but identified six organisational behaviours that influence decision-making. Ferrer et al. (2021) highlighted the importance of project governance mechanisms in decision-making. They stressed the importance of rationality in the decision-making process, which is underpinned by agency theory. Decisions can also be based on past experiences. Rational decision-making theory was used by Zarghami and Zwikael (2022) to measure project resilience. They made the case that decision-makers such as project managers should rely on quantitative information (past) to make informed decisions (future).
From a behavioural decision-making perspective, Stingl and Geraldi (2017) conducted an extensive systematic review. They provided an overview of how behaviours impact decisions and the associated coping mechanisms. They classified decisions into three groups, i.e. reductionist, pluralist and conceptualist. Decision-making complexity was investigated by Shi et al. (2020). They developed a comprehensive framework of decision-making complexity based on behavioural decision-making. In the same vain, Turner (2021) investigated how emotions impact the behaviour of project managers’ decisions. Hackman (2021) focused on the individual’s influence on project decision-making where perceptions were measured in behavioural decision-making. Cognitive challenges regarding decision-making when social media were involved were investigated by Ram and Titarenko (2022) through a social cognitive theory lens. They discovered that decision-making is impaired as not all information is always available in these situations. Literature focusing on decision-making from a theoretical perspective did not focus on benefits realisation or agile. This emphasises the first research gap.
From a more generic perspective, Okonedo (2018) investigated decision-making from an African viewpoint. He concluded that decisions are made based on communal thinking and consensus. Silvius et al. (2017) determined that when sustainability needs to be considered as part of decision-making, it does not play a huge role in the mind of project managers. Sustainability decisions are typically done at stage-gates. Distributed project teams are also phenomena that were investigated from a decision-making perspective. The success in managing distributed project teams is linked to team autonomy in conducting project activities and to formal decision-making processes (Bourgault et al., 2008). This was also investigated by McAvoy and Butler (2009) where the focus was on teams as decision-makers. This was based on the agile principles and they concluded that decisions are inter-related, with each decision leading to further decisions. Process theory was applied by Baker and Niederman (2023) in their quest to determine how project managers think when dealing with issues that have ethical considerations. They specifically favoured a more pragmatic approach than a decision model-based approach. Amin et al. (2023) applied principle-agent theory to determine how decisions are made within international development projects.
From an agile project management perspective, literature is emerging on how decisions are made. Thesing et al. (2021) introduced a decision model to decide which approach is more suitable to manage a project. Drury et al. (2012) identified five principles related to descriptive decision-making and mapped obstacles to these principles. This was done from the perspective of agile software development teams. The challenges of shared decision-making were highlighted by Moe et al. (2012). They also investigated agile software development teams and highlighted three challenges, i.e. the alignment of strategy with iterations, the allocation of resources and performing routine DevOPS activities in teams. Research highlighting the relationship between decision-making and principles focused on agile teams and not from a scaled agile perspective.
Although the project management literature is rich in decision-making, little or no attention is given to (1) decision-making and benefits realisation and (2) decision-making and agile. This highlights the need to investigate benefits realisation decision-making in a scaled agile environment.
2.3 Benefits realisation
The focus of benefits realisation is to harvest value from the product or service that is created by a project. Benefits realisation is associated with value creation and not necessarily how project management performance is measured (Serra and Kunc, 2015). It is typically done after the closure of the project in an environment where a predictive (waterfall) approach is used. Benefits realisation typically follows a process- or rule-based approach. A process-based approach prescribes the steps or rules that must be followed to achieve an outcome. In the case of benefits realisation, the outcome is to harvest benefits from the product or service delivered by a project. Figure 1 highlights various authors’ perceptions of how benefits realisation should be managed from a process-based perspective. It is evident that there are various perspectives of how to apply rules to harvest benefits and that there is no single perspective. These perspectives focus on the processes, i.e. a process-based view (Bose, 2012).
Two problems are associated with process-based benefits realisation. The first is that organisations are not good at performing benefits realisation per se. The study of Holgeid and Jørgensen (2020) found that 75% of organisations adopt benefits realisation versus an average of 38% across seven other similar studies (Jørgensen, 2016; Lin and Pervan, 2003; Smith et al., 2008). The reasons for this low adoption rate include no formula to measure target benefits (Chih and Zwikael, 2015; Zwikael and Meredith, 2019), the failure to identify who is responsible for benefits realisation (Romero-Torres, 2021; Zwikael et al., 2019) and the failure to adhere to the processes (Marnewick, 2016; Smith et al., 2008), to name but a few.
The second problem is that organisations are not getting the benefits or values of their IT investments. Organisations are not good at realising benefits when they follow a process-based approach to benefits realisation (Svejvig and Schlichter, 2020). The Project Management Institute (2019) estimates the percentage of organisations that realise benefits at between 56 and 78%. In a South African study, Khoza and Marnewick (2020) determined that only two-thirds of identified benefits were realised, irrespective of whether a predictive (waterfall) or iterative (agile) approach was followed. These results highlight that there is a potential problem in the way that benefits are realised when a process-based approach is followed.
Little or no research is available on benefits realisation management in an agile environment. Research focuses exclusively on the value or benefits of agile implementations (Gustavsson, 2016; Kamei et al., 2017) rather than the process of benefits realisation within an agile environment. In their article focusing on benefits realisation in an agile environment, Marnewick and Marnewick (2022) identify principles for managing benefits realisation. Although this study highlights some principles, it fails to identify whether benefits are realised more than in non-agile environments. Reich and Peppard (2022) caution that “incremental delivery does not translate into immediate delivery of benefits”.
There is a clear difference between how benefits realisation should be managed from a principle-based perspective versus a process-based perspective. The principle-based perspective enables project leaders to focus on what is necessary to create value or benefits. When a process-based perspective is followed, the focus is on the processes, and the end goal of creating value is lost. Empirical data shows that irrespective of whether process-based (utilitarianism) or principle-based (deontology), benefits are not realised and organisations are not getting the promised value from their IT investments.
The literature review confirms the first research gap, i.e. the misalignment between agile (principle-based) and benefits realisation (process-driven). Benefits realisation is based on processes as illustrated in Figure 1 which in turn is informed by descriptive decision theory. Agile per se is based on principles which is informed by normative decision theory. There is a direct clash between these decision theories and therefor a direct clash how benefits are realised in an agile environment.
The research methodology that was used to answer the stated research questions is elaborated on in the next section.
3. Research methodology
3.1 Data collection
A qualitative approach was applied to answer the research questions. Because the research was exploratory, this approach was applicable (Yin, 2014). A semi-structured interview guide was developed based on previous studies on benefits realisation management (Marnewick, 2016), as well as constructs from agile and scaled agile. The semi-structured interview consisted of 24 questions divided into four sections, but only one section is applicable to this article. This section focused on the agile benefits realisation process. Cunningham (2008) and Kwok and Ku (2008) suggest semi-structured interviews as an appropriate method to gather information. During an interview, interviewees are given the opportunity to elaborate in a way that is not possible with other methods such as questionnaires, but they are able to share information in their own words and from their own perspectives. Interviews were conducted virtually using Microsoft Teams. Purposive sampling was used to identify the interviewees based on their participation within an agile project management office (PMO) community of practice, as well as their roles within their respective organisations’ agile transition. Table 1 provides a summary of the interviewees. In some instances, multiple views were collected from the same organisation.
3.2 Data analysis
The recorded Microsoft Teams video files were transcribed verbatim using Microsoft Teams’ built-in transcription functionality. After this, the original transcription was edited by listening to the recordings. The transcriptions went through an iterative process of open coding which summarised the data into smaller meaningful units called codes and themes (Saldana, 2013; Williams and Moser, 2019). ATLAS.ti was used to facilitate the coding process. The purpose of the coding process was to identify potential principles.
An inductive approach was applied in the data analysis to identify first-order concepts and second-order themes, which were mapped against the scaled agile levels (Gioia et al., 2013). The first-order concepts and second-order themes were inductively derived based on the following three-step process (Lewins and Silver, 2008; Von Seggern and Young, 2003):
- (1)
Perform open coding: Small segments of data are considered in detail and compared with one another. This step generates large volumes of codes, which encapsulate the notion of “what is going on”.
- (2)
Perform axial coding: All the codes generated are analysed. Codes are rethought in terms of similarity and difference and consolidated where appropriate.
- (3)
Perform selective coding: The researchers revisit the codes once more. The instances in the data which pertinently illustrate themes and concepts are identified. Conclusions are validated by illustrating instances represented by and grounded in the data.
Twelve principles were identified through the coding process and 118 associated verbatim quotations were highlighted. ATLAS.ti’s coding and co-occurrence matrices were used to identify relationships between codes (principles) (Saldana, 2013). This is highlighted in Figure 2.
Based on the co-occurrence matrices, causal loop diagrams were used in this study to indicate an understanding of and relationship between the identified principles. McLucas (2003) defines these diagrams as “a convenient way of representing the principle feedback loops and related causal relationships relevant to a particular problem situation, without distinguishing between the nature of the interconnected variables”. A causal loop diagram provides an understanding of the presence of reinforcing (positive) and balancing (negative) causal relationships. A positive relationship implies that when variable A increases or decreases, variable B should increase or decrease. Negative relationships mean that when variable A increases, variable B should decrease, or when variable A decreases, variable B should increase. Various symbols are used to explain the relationship between the variables. An arrow with a positive sign (→ +) explains a positive relationship, and an arrow with a negative sign (→ -) explains a negative relationship. In addition, a continuous increase/decrease (growth/decline) of both variables is indicated by the “R” symbol in a closed or partially curved arrow () indicating a reinforcing feedback loop. A balancing feedback loop is indicated by the “B” symbol in a closed or partially curved arrow (). Within a balancing feedback loop, the decrease of one variable forces the other variable to increase (Dhirasasna and Sahin, 2019; Schaffernicht, 2010).
The use of causal loop diagrams has been cited in different studies, including those on project management (Toole, 2005), stakeholder management (Dhirasasna and Sahin, 2019) and information systems (Odiit et al., 2014).
4. Results
The results are discussed based on the levels of scaled agile, i.e. portfolio, planning and prioritisation (programme) and team or implementation.
4.1 Portfolio level
The principle that defines the other principles in agile benefits realisation management is beyond budgeting. Beyond budgeting is a management control system that seeks to improve performance using flexible sense-and-respond mechanisms (Hope and Fraser, 2003; Nguyen et al., 2018). Respondent CVO-1 had the following to say about beyond budgeting: “And in the principle of beyond budgeting, you focus more on metrics measures and progress associated with it”, and added, “So the principle of beyond budgeting is that as an organization you’ve identified a set of measures that would reflect whether the organization is being successful or not”. Based on this statement, two other principles are influenced, i.e. behavioural change and define target outcomes.
- (1)
“Ah, what you would have is that people will adopt Uhm, behaviours that are aligned to the organisational culture” [PART-1]. If the organisational culture changes from traditional budgeting to beyond budgeting and fixed capacity, then it will positively change behaviour. This behavioural change was supported by CVO-1: “But what I have started to see is through this cadence we’ve actually started to see a change in behaviours with people are starting to think differently around.” Changing behaviours is not an easy feat, as attested to by IT-1: “The behaviour around those kinds of things is something we haven’t cracked and I’m not sure if we have the will to kind of crack it, but that drives certain things, right?”
- (2)
When it comes to defining the target outcomes, IT-1 commented that “those kinds of levers are that we’re trying to ascertain and because they bake it into their forecasts in terms of their budget them achieving or not achieving is then directly linked to actually achieving those outcomes and you kind of both vested into the same outcome in kind of in that game”. This view was supported by PART-1: “Owners and responsibilities have been assigned to realise and verify key business benefits and project outcomes.”
There is a two-way relationship between define target outcomes and course correction. The target outcomes should enforce a course correction; in other words, if the targets change, then corrections should be made to accommodate and facilitate these target changes. “If you starting to see if you started to see the uptake in customers but it’s not correlating in a financial outcome, you should be able to course correct quite rapidly to say, well, why did I go wrong and how do I correct the process” [CVO-1]. But if the organisation is not correcting the course, then it will imply that the defined target outcomes will not be realised. Behavioural change has a positive impact on the principle of consequence management.
The principle of consequence management relies on the fact that decisions do have consequences: “… and then the second challenge is consequence management and by consequence management, it doesn’t have to be punitive and but if there’s non valued, what are the consequences on non-value?” [CVO-1]. Consequence management is also influenced by the visibility principle. “So through bringing visibility you’ve increased accountability of the people that are asking for the value to be delivered because they potentially know, or they will likely be asked to demonstrate what this is meant for the organisation, etc.” [CONS-1]. Apart from accountability, visibility also enables product owners and the organisation at large to view progress: “they could then like right there every day see what the teams doing get feedback, give direction to that you know. So I think that created a lot more visibility of how we’re actually progressing” [PMO-1]. Decisions and the results (positive or negative) are made visible. This visibility should then positively influence behaviour, as people do not want to be viewed as making the wrong decisions. Visibility should then enforce a culture of “comply or explain”, which is in line with normative decision theory (Bell et al., 1988). Visibility is typically ensured through an enterprise visibility room (EVR). An EVR focuses on a single, prioritised, enterprise backlog of strategic outcomes. It visualises the active strategic work and which teams are engaged in delivering that value. The principles course correction and visibility also have a positive influence on each other. When course correction is done due to the changes in the defined target outcomes, then these changes should be reflected in the EVR for all to observe.
Figure 3 presents the principles applicable to the portfolio level. There are two feedback loops. The first feedback loop is a reinforcing loop between visibility and consequence management. The more visibility, the more people will take accountability for their actions and decisions. This relates to the notion of “comply or explain” governance. The second feedback loop is a balancing loop between define target outcomes and course correction. Corrective action needs to occur based on the defined target outcomes. But when the desired outcomes are not achieved, then course correction needs to take place, which will have a negative impact on the defined target outcomes.
The next level is the level where planning and prioritisation of work are done.
4.2 Planning and prioritisation level
The second level focuses on the planning and prioritisation of work and/or projects. This is typically done at a program increment (PI).
The first principle at this level focuses on customer journeys. Customer journeys entail the holistic experience of the organisation’s customers. They involve a visual depiction of the sequence of events through which customers interact with the organisation (Rosenbaum et al., 2017). Benefits need to be mapped to customer journeys to maximise the value of the investments, but also to create value for the customer (Marnewick and Marnewick, 2022). PART-1 summarised customer journeys as follows: “In the past you would have a client centric sort or product centric approach to business. Now it’s moved into a client centric approach servicing the client, but then making sure that the customer journey is less painful and those would be there’s some qualitative and quantitative benefits in that so flexibility around revenue.” Customer journeys also need to be visible: “but I think the conversation is much more kind of starting to get more data driven and figure out how do we get those metrics in to say did we get the customer appetite and are we on the right direction? So we are busy doing a lot more things like running spikes and proof of concepts and kind of testing the market a little bit and then kind of deciding where they’re so” [IT-1]. Through the visibility of the metrics, the value creation for the customer can be visually tracked. As with the portfolio level, there is a two-way positive causality between the principles of consequence management and visibility.
Benefits and value associated with projects need to be continuously monitored to determine whether the projects are still on track to deliver the intended benefits. “So these values session if I can call it, it’s a validation session between the principle BA and then the product owner or the business owner to kind of confirm that the whether it’s a short term or whether it’s a long term that gets dictated based on the user story, but that’s being delivered or there is a refinement discussion to identify maybe there’s a bit of extra OK” [CHANGE-1]. TRAN-1 felt that “if you look at it from a continuous improvement perspective with success stories telling what made us successful in such a way that other people can do it as well, because that’s what we want to do with all of this is we want to make everybody successful or not”.
Continuous monitoring as a principle has a two-way positive relationship with the principle of consequence management. Although the interviewees did not explicitly highlight this causality, it can be inferred that when continuous monitoring highlights that value or benefits will not be realised, it will have consequences, and based on the results of consequence management, efforts to improve continuous monitoring will be put in place.
The last principle at this level is consistency. “Consistency you’ve got to have those ceremonies right? So once a quarter, what is the process, what’s happened? What’s being delivered?” [CVO-1]. This principle has a positive causality on continuous monitoring. The implementation of consistent ceremonies like PIs or retrospectives creates a platform where benefits realisation is consistently monitored. The purpose of the ceremonies is to measure performance.
Figure 4 presents the principles applicable to the planning and prioritisation level. There are two reinforcement feedback loops. As with the portfolio level, there is a reinforcement feedback loop between visibility and consequence management. The reinforcement loop between consequence management and continuous monitoring emphasises the importance of continuous monitoring.
The next level is the level where the team itself is responsible for the creation of the artefact.
4.3 Implementation level
This level focuses on the creation of the product that should create value for the customer. The first principle that governs this level is cross-functional teams. Cross-functional teams consist of members from different functional areas. They are thought to facilitate the product development process because they bring together people from different disciplines and functions that have pertinent expertise about the proposed innovation problems (Chen, 2007). The importance of cross-functional teams is highlighted in the following quotes:
- (1)
“I would say the teams that do well are all the high performing teams. Uh, maybe they’ve got the right culture. They’ve got the right mindsets, they trust each other to do what needs to be done, and if problems happen, they don’t hold an individual accountable. They hold the team accountable so it’s that trust it’s that respect.” [COACH-1]
- (2)
“because that’s also quite important with agile is that because you’ve got cross-functional teams it helps you to define your business benefits in a lot more detail. Uhm, I mean if you if you think about all of these, that is organisational wide. And if you’ve got a cross-functional team, it helps you with that and then also with the benefit map and then with putting measurement criteria in place.” [PART-1]
The fact that team members trust one another implies that the team is accountable for any failures. This speaks directly to the team taking ownership of the consequences (positive or negative) of their actions.
Within an agile environment, cross-functional teams are collocated. Green et al. (2010) explain that collocation involves face-to-face communication, quick feedback and informal interaction. Visibility is improved due to collocation as teams typically make use of Kanban boards to indicate the progress of their work and the project (Laanti and Kangas, 2015). This is usually enforced through ceremonies such as retrospectives. The ceremonies at implementation level are required to be performed consistently. As with the other two levels, there is a positive causality between consequence management and visibility.
A principle that was also highlighted is the notion of build-own-run. In essence, it implies that the team is responsible for the entire product, i.e. from conception into production. This also relates to the consequence management principle where the team then takes ownership if the product “breaks” the operational functioning of the organisation. Adopting the principle of build-own-run involves changing processes and people mindsets (Marnewick and Langerman, 2021). This was supported by PART-1, who stated, “Where in this case what would happen with agile is that you would embed your team so you would have cross-functional teams that would be operating within the business uhm, affecting that change, so that is quite a big operating model change because you are now building and running at the same time”. There are benefits associated with this principle: “but we also are teams on our doing you build it you run it you own it. So there’s a lot of benefits that we measure in terms of your ability to repair and kind of respond to changes and those kind of things too. So it’s not just around whether your team is getting the internal investments. Also, the sustainability of the team and the health of the team and also the health and stability of the system” [IT-1].
The architectural runway principle can have either a positive or a negative influence on the build-own-run principle. “And the moment you try to just apply agile in a narrow sense and you say well I’m going to just deliver product but not look at my architecture runway at the back and my capabilities at the back. Then what’s gonna happen? You’re gonna run out of runway, meaning the system can’t do it anymore” [PART-1]. PMO-1 extended this even further and applied this principle to the team itself and not just the technology: “What I would love to see is much more what Agile is truly about, where it’s proper product experimentation where business owners are given time and teams are capacity and say you know, you know we want to do something in the gym space try come up with something cool that drives engagement and then they experiment with their team but they know they’ve got a capacity in a budget and that runway of work that they can try experiment with.”
Figure 5 presents the principles applicable to the implementation level. There are three feedback loops. As with the other two levels, there is a reinforcement feedback loop between visibility and consequence management, and also between visibility and consistency. Visibility of work and progress ensures consistency of the work, and because artefacts delivered are consistently of a high quality, this is reflected in the progress of the project. There is a balancing feedback loop between Build-Own-Run and the architectural runway. If the enterprise architecture is not well planned and implemented, then solutions cannot be delivered.
5. Discussion
The first research question focused on the influence of decision-making on the adoption of a principle-based approach to agile benefits realisation. Decision-making is founded on ethical and decision theories. Deontology as an ethical theory facilitates principle-based benefits realisation. People accountable for benefits realisation should evaluate all decisions related to benefits realisation to the degree to which the decisions provide acceptable rational choice. In other words, decisions must be made that are always applicable within all situations. A rule-based approach to benefits realisation might lead to different interpretations and create inconsistencies.
It is evident that the interviewees followed a normative or rational decision-making process. This is in line with the research of Małecka (2020) who concluded that project managers should behave or operate in a certain way and manner and make choices based on this behaviour. Ceremonies such as programme increments and sprints allow for rational decision-making. These ceremonies are not process- or rule-based and therefore allow team members to apply certain principles and logical thinking in making decisions regarding benefits realisation. The results are also in line with McAvoy and Butler (2009) who found that decisions are interrelated. The interviewees made it clear that decisions do influence or impact other decisions or behaviour later in the project. Decisions are not made in isolation and therefore a process-based approach is not the preferred way of making decisions. Decisions should be made by being based on principles that guide decision-making.
The second research question focused on the principles that drive benefits realisation in a scaled agile environment. Seventeen principles were identified. Realising benefits in an environment in which a predictive project management approach such as waterfall is used is challenging as not all benefits are realised. Benefits realisation in an iterative approach such as agile is even more complicated, as agile is built upon principles and not processes and rules. Historically, project management has been based on processes and rules. The reason might be that project management originated from the engineering and construction industries. These industries are typically process or rules driven. As stated by Bose (2012), different thinking is needed. The alternative is principles that are founded in deontology. Various principles and their relationships with other principles were identified in this study. The two principles that are applicable to all three levels of scaled agile are consequence management and visibility. Visibility is achieved through the implementation of EVRs and the use of Kanban boards (Laanti and Kangas, 2015). Since everything is visible, the natural outflow is consequence management. Failures or lack of progress cannot be hidden, as everything is visible to everyone. Sama and Shoaf (2005) mention that “clans rely on social controls, executed through some set of common beliefs or concordant interests, to reduce the incidence of opportunistic behaviour. The application of rules is substituted by an application of principles, norms and traditions that are commonly understood and respected in society”. This statement supports the notion of self-governance of “comply or explain” within a scaled agile environment.
Another principle at the planning and prioritisation as well as the implementation levels is consistency. Ceremonies like PIs, daily stand-ups and retrospectives need to be performed in a consistent way. These form the backbone of the agile mindset and are therefore important in the realisation of benefits, especially where PIs are concerned.
The remaining identified principles play a role in the realisation of benefits, but it is up to the organisation to decide which principles are applicable. Applicable principles need to be applied based on “comply or explain” and not on the basis of “comply or else”. “Comply or explain” also relates to the 12 principles of the Agile Manifesto.
Deontology and utilitarianism are two distinct ethical frameworks that guide decision-making in various fields, including project management. These philosophical perspectives offer different approaches to assessing the moral implications of actions and making ethical choices. In the context of project management, understanding the differences between deontology and utilitarianism is crucial for project managers to navigate complex ethical dilemmas.
Decision-making in an agile environment is between a choice of two opposing facts or values which typically excludes one in favour of the other. Choosing the “right” outcome or the best possible solution is deeply rooted in ethics (Van Staveren, 2007). Ethics per se can be defined as the moral principles that govern an individual’s behaviour, guiding them in distinguishing between right and wrong actions and shaping their decisions and conduct in various contexts. Ethics is thus practical knowledge rooted in experience rather than just theoretical knowledge. Practical wisdom, being both an ethical virtue and an intellectual one, must be acquired through practice and is not just about applying general understanding to specific situations.
6. Conclusions
This article focused on the introduction of an alternative view for realising benefits in a scaled agile environment. Historically, benefits realisation has been process or rule driven, and little or no research has been done on how benefits should be realised in a scaled agile environment. The Agile Manifesto is based on 12 principles and the Project Management Institute has introduced principles in the latest edition of the PMBoK® Guide. This has opened the door for an alternative approach to benefits realisation that is based on principles.
6.1 Practical contribution
Twelve principles were identified with two principles, visibility and consequence management, featuring in all three levels of scaled agile. These two principles are non-negotiable and should be the foundation upon which agile benefits realisation is built. Consistency is important in the planning and prioritisation as well as the implementation levels. The focus is on the consistency of performing ceremonies. Consistency is key in a principle-based environment as behaviour should always be the same, irrespective of the environment. This is applicable to decision-making and performing of ceremonies. The implementation of the remainder of the principles is left to the discretion of the organisation. One such principle is beyond budgeting. Not all organisations are ready to go this route and thus it can be excluded until required.
6.2 Theoretical contribution
This article contributes in various ways to the current body of knowledge on benefits realisation. Firstly, a novel approach to agile benefits realisation is introduced. Principle-based instead of rule-based agile benefits realisation is proposed. Principle-based agile benefits realisation opens the door for consequent decisions, irrespective of the business environment or political agendas. Each organisation will apply the principles, taking into consideration their own specific context. Secondly, this article also contributes to the current thinking around principles versus processes or rules. From an IT or agile perspective, principles were introduced more than 20 years ago with the creation of the Agile Manifesto. Twelve principles were introduced to manage the development of software and increase the success rates of software development projects and ultimately IT projects. In line with this, the Project Management Institute has also introduced principles in the 7th edition of the PMBoK® Guide. “Principle statements provide broad parameters within which project teams can operate and offer many ways to remain aligned with the intent of the principles” (Project Management Institute, 2021, p. xi). Another contribution is to the field of benefits realisation. As highlighted earlier, no research has been done regarding decision-making and benefits realisation. This article contributes to closing this gap through the introduction of normative decision-making in the realisation of benefits.
6.3 Future research
By no means were all principles identified. Future research will focus on engaging other interviewees and trying to uncover additional principles that were not identified during this round of interviews. The focus of these interviews was on benefits realisation in a scaled agile environment. Future research might also investigate the role of principles in a more traditional project management environment. Although SAFe is the most popular scaled agile framework, future research can also focus on how benefits are realised in other scaled agile frameworks such as DAD and Scrum@Scale.
Arjoon (2006) has the last word. He warns that an optimal balance should be struck between rule-based and principle-based approaches. Although principles should be used to realise benefits in a scaled agile environment, organisations should also have a rule-based focus when it comes to the adherence of methodologies such as Scrum. A fine balance is needed to decide between principles and rules.
Figures
Summary of interviewees
Case | Rolea | Identifier | Scaled agile framework implemented | Agile experience (years) | Duration | Pages |
---|---|---|---|---|---|---|
Financial institution (1) | Head of PMO | PMO-1 | SAFe | 11 | 00:53:30 | 14 |
Head of transformation | TRAN-1 | SAFe | 8 | 00:45:38 | 11 | |
Consulting | Partner | PART-1 | SAFe | 11 | 01:23:49 | 18 |
Financial institution (2) | Business IT executive | IT-1 | SAFe | 10 | 00:57:45 | 16 |
Entertainment company | Change manager | CHANGE-1 | SAFe | 2 | 01:03:29 | 17 |
Business transformation | TRAN-2 | 2 | ||||
Consultant | CONS-1 | 10 | ||||
Financial institution (3) | Chief value officer | CVO-1 | SAFe | 7 | 00:39:18 | 11 |
IT outsourcing | Agile coach | COACH-1 | SAFe | 10 | 0033:06 | 10 |
Note(s): aThe interviewees’ role does not necessarily match the roles as prescribed by SAFe. This is due to each organisation’s unique adoption and implementation of SAFe. Realising benefits is typically associated with managerial roles and not technical roles
Source(s): Authors’ own work
References
Alqudah, M. and Razali, R. (2016), “A review of scaling agile methods in large software development”, International Journal of Advanced Science, Engineering and Information Technology, Vol. 6 No. 6, pp. 828-837, doi: 10.18517/ijaseit.6.6.1374.
Amin, H., Scheepers, H. and Malik, M. (2023), “Project monitoring and evaluation to engage stakeholders of international development projects for community impact”, International Journal of Managing Projects in Business, Vol. 16 No. 2, pp. 405-427, doi: 10.1108/IJMPB-02-2022-0043.
Arjoon, S. (2006), “Striking a balance between rules and principles-based approaches for effective governance: a risks-based approach”, Journal of Business Ethics, Vol. 68 No. 1, pp. 53-82, doi: 10.1007/s10551-006-9040-6.
Ashurst, C. (2011), Benefits Realization from Information Technology, Palgrave Macmillan, Virginia, available at: http://www.palgrave.com/products/title.aspx?pid=491116
Baker, E.W. and Niederman, F. (2023), “Practitioner application of ethics in ethical decision-making within projects: a process theory view”, Project Management Journal, Vol. 54 No. 4, pp. 334-348, doi: 10.1177/87569728231166917.
Bell, D.E., Raiffa, H. and Tversky, A. (1988), Decision Making: Descriptive, Normative, and Prescriptive Interactions, Cambridge University Press, Cambridge. doi: 10.1017/CBO9780511598951.
Bose, U. (2012), “An ethical framework in information systems decision making using normative theories of business ethics”, Ethics and Information Technology, Vol. 14 No. 1, pp. 17-26, doi: 10.1007/s10676-011-9283-5.
Bourgault, M., Drouin, N. and Hamel, É. (2008), “Decision making within distributed project teams: an exploration of formalization and autonomy as determinants of success”, Project Management Journal, Vol. 39 S1, pp. S97-S110, doi: 10.1002/pmj.20063.
Bradley, B. (2010), Benefit Realisation Management: A Practical Guide to Achieving Benefits through Change, 2nd ed., Gower Publishing, available at: http://www.gowerpublishing.com/default.aspx?page=637&calcTitle=1&title_id=9972&edition_id=12831
Chen, C. (2007), “Information technology, organizational structure, and new product development---The mediating effect of cross-functional team interaction”, IEEE Transactions on Engineering Management, Vol. 54 No. 4, pp. 687-698, doi: 10.1109/TEM.2007.906831.
Chih, Y.-Y. and Zwikael, O. (2015), “Project benefit management: a conceptual framework of target benefit formulation”, International Journal of Project Management, Vol. 33 No. 2, pp. 352-362, doi: 10.1016/j.ijproman.2014.06.002.
Cohen, B.J. (1996), “Is expected utility theory normative for medical decision making?”, Medical Decision Making, Vol. 16 No. 1, pp. 1-6, doi: 10.1177/0272989X9601600101.
Cunningham, W.S. (2008), “Voices from the field: practitioner reactions to collaborative research initiatives”, Action Research, Vol. 6 No. 4, pp. 373-390, doi: 10.1177/1476750308097025.
Dhirasasna, N. and Sahin, O. (2019), “A multi-methodology approach to creating a causal loop diagram”, Systems, Vol. 7 No. 3, pp. 1-36, doi: 10.3390/systems7030042.
Dingsøyr, T., Nerur, S., Balijepally, V. and Moe, N.B. (2012), “A decade of agile methodologies: towards explaining agile software development”, Journal of Systems and Software, Vol. 85 No. 6, pp. 1213-1221, doi: 10.1016/j.jss.2012.02.033.
Doherty, N.F., Ashurst, C. and Peppard, J. (2012), “Factors affecting the successful realisation of benefits from systems development projects: findings from three case studies”, Journal of Information Technology, Vol. 27 No. 1, pp. 1-16, doi: 10.1057/jit.2011.8.
Drury, M., Conboy, K. and Power, K. (2012), “Obstacles to decision making in Agile software development teams”, Journal of Systems and Software, Vol. 85 No. 6, pp. 1239-1254, doi: 10.1016/j.jss.2012.01.058.
Einhorn, F., Marnewick, C. and Meredith, J. (2019), “Achieving strategic benefits from business IT projects: the critical importance of using the business case across the entire project lifetime”, International Journal of Project Management, Vol. 37 No. 8, pp. 989-1002, doi: 10.1016/j.ijproman.2019.09.001.
Ferrer, P.S.S., Araújo Galvão, G.D. and Monteiro de Carvalho, M. (2021), “The missing link in project governance: permeability and influence of governance precepts on decision making in the project domain”, Project Management Journal, Vol. 52 No. 1, pp. 45-60, doi: 10.1177/8756972820941649.
Ford, C.L. (2008), “New governance, compliance, and principles-based securities regulation”, American Business Law Journal, Vol. 45 No. 1, pp. 1-60, doi: 10.1111/j.1744-1714.2008.00050.x.
Gioia, D., Corley, K. and Hamilton, A. (2013), “Seeking qualitative rigor in inductive research”, Organizational Research Methods, Vol. 16 No. 1, pp. 15-31, doi: 10.1177/1094428112452151.
Green, R., Mazzuchi, T. and Sarkani, S. (2010), “Communication and quality in distributed agile development: an empirical case study”, World Academy of Science, Engineering and Technology, Vol. 61, pp. 322-328, available at: https://citeseerx.ist.psu.edu/document?repid=rep1&type=pdf&doi=0bace5b1f402aae72668f62768770d43bb228d4d
Gustavsson, T. (2016), “Benefits of agile project management in a non-software development context - a literature review”, PM World Journal, Vol. V No. VIII, pp. 1-12.
Hackman, D.C. (2021), “Quantifying heterogeneous individual perceptions in project management research”, International Journal of Managing Projects in Business, Vol. 14 No. 5, pp. 1163-1184, doi: 10.1108/IJMPB-04-2020-0114.
Harrison, E.F. and Pelletier, M.A. (2000), “The essence of management decision”, Management Decision, Vol. 38 No. 7, pp. 462-470, doi: 10.1108/00251740010373476.
Holgeid, K.K. and Jørgensen, M. (2020), “Benefits management and agile practices in software projects: how perceived benefits are impacted”, 2020 IEEE 22nd Conference on Business Informatics (CBI), Antwerpen, Belgium.
Hope, J. and Fraser, R. (2003), Beyond Budgeting, Harvard Business School Press, Boston.
Idler, B.D. and Spang, K. (2019), “IT project decisions: conclusions and recommendations for corporate practice”, International Journal of Managing Projects in Business, Vol. 12 No. 4, pp. 1030-1060, doi: 10.1108/IJMPB-04-2018-0082.
Jørgensen, M. (2016), “A survey on the characteristics of projects with success in delivering client benefits”, Information and Software Technology, Vol. 78, pp. 83-94, doi: 10.1016/j.infsof.2016.05.008.
Kamei, F., Pinto, G., Cartaxo, B. and Vasconcelos, A. (2017), “On the benefits/limitations of agile software development: an interview study with Brazilian companies”, 21st International Conference on Evaluation and Assessment in Software Engineering, Karlskrona, Sweden.
Keren, G.B. and Wagenaar, W.A. (1985), “On the psychology of playing blackjack: normative and descriptive considerations with implications for decision theory”, Journal of Experimental Psychology: General, Vol. 114 No. 2, pp. 133-158, doi: 10.1037/0096-3445.114.2.133.
Khoza, L. and Marnewick, C. (2020), “Waterfall and Agile information system project success rates – a South African perspective”, South African Computer Journal, Vol. 32 No. 1, pp. 43-73, doi: 10.18489/sacj.v32i1.683.
Khoza, L. and Marnewick, C. (2021), “Challenges and success factors of scaled agile adoption – a South African perspective”, The African Journal of Information Systems, Vol. 13 No. 2, pp. 164-185, available at: https://digitalcommons.kennesaw.edu/ajis/vol13/iss2/2.
Kransdorff, A. (1996), “Using the benefits of hindsight - the role of post-project analysis”, The Learning Organization, Vol. 3 No. 1, pp. 11-15, doi: 10.1108/09696479610106763.
Kwok, J. Y.-c. and Ku, H.-B. (2008), “Making habitable space together with female Chinese immigrants to Hong Kong: an interdisciplinary participatory action research project”, Action Research, Vol. 6 No. 3, pp. 261-283, doi: 10.1177/1476750308094131.
Laanti, M. and Kangas, M. (2015), “Is agile portfolio management following the principles of large-scale agile? Case study in Finnish broadcasting company Yle”, 2015 Agile Conference, Vol. 353, pp. 92-96, doi: 10.1109/agile.2015.9.
Lewins, A. and Silver, C. (2008), Using Software in Qualitative Research, Sage Publications, London.
Lin, C. and Pervan, G. (2003), “The practice of IS/IT benefits management in large Australian organizations”, Information and Management, Vol. 41 No. 1, pp. 13-24, doi: 10.1016/S0378-7206(03)00002-8.
Małecka, M. (2020), “The normative decision theory in economics: a philosophy of science perspective. The case of the expected utility theory”, Journal of Economic Methodology, Vol. 27 No. 1, pp. 36-50, doi: 10.1080/1350178X.2019.1640891.
Marnewick, C. (2016), “Benefits of information system projects: the tale of two countries”, International Journal of Project Management, Vol. 34 No. 4, pp. 748-760, doi: 10.1016/j.ijproman.2015.03.016.
Marnewick, C. and Langerman, J. (2021), “DevOps and organizational performance: the fallacy of chasing maturity”, IEEE Software, Vol. 38 No. 5, pp. 48-55, doi: 10.1109/MS.2020.3023298.
Marnewick, C. and Marnewick, A.L. (2022), “Benefits realisation in an agile environment”, International Journal of Project Management, Vol. 40 No. 4, pp. 454-465, doi: 10.1016/j.ijproman.2022.04.005.
McAvoy, J. and Butler, T. (2009), “The role of project management in ineffective decision making within Agile software development projects”, European Journal of Information Systems, Vol. 18 No. 4, pp. 372-383, doi: 10.1057/ejis.2009.22.
McLucas, A.C. (2003), Decision Making: Risk Management, Systems Thinking and Situation Awareness, Argos Press Pty, Yarralumla.
Moe, N.B., Aurum, A. and Dybå, T. (2012), “Challenges of shared decision-making: a multiple case study of agile software development”, Information and Software Technology, Vol. 54 No. 8, pp. 853-865, doi: 10.1016/j.infsof.2011.11.006.
Nguyen, D.H., Weigel, C. and Hiebl, M.R.W. (2018), “Beyond budgeting: review and research agenda”, Journal of Accounting and Organizational Change, Vol. 14 No. 3, pp. 314-337, doi: 10.1108/JAOC-03-2017-0028.
Odiit, M.C.A., Mayoka, G.K., Rwashana, A.S. and Ochara, N.M. (2014), “Alignment of Information Systems to strategy in the health sector using a systems dynamics approach”, Proceedings of the Southern African Institute for Computer Scientist and Information Technologists Annual Conference 2014 on SAICSIT 2014 Empowered by Technology, Centurion, South Africa, Vol. 50, pp. 38-49, doi: 10.1145/2664591.2664624.
Okonedo, E. (2018), “Decision-making practices in Africa”, in Indigenous Management Practices in Africa, Emerald Publishing, Vol. 20, pp. 221-247, doi: 10.1108/S1877-636120180000020012.
Peterson, M. (2017), An Introduction to Decision Theory, 2nd ed., Cambridge University Press, Cambridge, doi: 10.1017/9781316585061.
Project Management Institute (2016), Establishing Benefits Ownership and Accountability (Thought Leadership Series, Issue, P. M. Institute, available at: http://www.pmi.org/learning/thought-leadership/series/benefits-realization/establishing-benefits-realization-ownership-accountability
Project Management Institute (2019), Benefits Realization Management: A Practice Guide. Project Management Institute, Newton, PA, available at: https://www.pmi.org/pmbok-guide-standards/practice-guides/benefits-realization?utm_source=pmi&utm_medium=website&utm_term=DXP7409&utm_content=HomePage_HeroImage&utm_campaign=Standards2019&utm_aud=PMIwebsite&utm_thm=Standards_BenefitsRealization&utm_sdte=01_15_16&utm_dep=mkt
Project Management Institute (2021), A Guide to the Project Management Body of Knowledge (PMBOK Guide), 7th ed., Project Management Institute, Newton, PA.
Ram, J. and Titarenko, R. (2022), “Using social media in project management: behavioral, cognitive, and environmental challenges”, Project Management Journal, Vol. 53 No. 3, pp. 236-256, doi: 10.1177/87569728221079427.
Reich, B.H. and Peppard, J. (2022), “Realizing value from digital transformation: benefits management re-imagined”, 2022 Portland International Conference on Management of Engineering and Technology (PICMET), Portland, OR, USA, Vol. 6, pp. 1-8, doi: 10.23919/picmet53225.2022.9882702.
Romero-Torres, A. (2021), “Enabling the project owner role for benefits realization management: a case study of an IT project in a public organization”, Journal of Modern Project Management, Vol. 9 No. 1, pp. 204-217, doi: 10.19255/JMPM02614.
Rosenbaum, M.S., Otalora, M.L. and Ramírez, G.C. (2017), “How to create a realistic customer journey map”, Business Horizons, Vol. 60 No. 1, pp. 143-150, doi: 10.1016/j.bushor.2016.09.010.
Saldana, J. (2013), The Coding Manual for Qualitative Researchers, 2nd ed., SAGE Publications, London, available at: http://www.uk.sagepub.com/books/Book237888?siteId=sage-uk&prodTypes=any&q=the+coding+manual&fs=1
Sama, L.M. and Shoaf, V. (2005), “Reconciling rules and principles: an ethics-based approach to corporate governance”, Journal of Business Ethics, Vol. 58 No. 1, pp. 177-185, doi: 10.1007/s10551-005-1402-y.
Schaffernicht, M. (2010), “Causal loop diagrams between structure and behaviour: a critical analysis of the relationship between polarity, behaviour and events”, Systems Research and Behavioral Science, Vol. 27 No. 6, pp. 653-666, doi: 10.1002/sres.1018.
Serra, C.E.M. and Kunc, M. (2015), “Benefits realisation management and its influence on project success and on the execution of business strategies”, International Journal of Project Management, Vol. 33 No. 1, pp. 53-66, doi: 10.1016/j.ijproman.2014.03.011.
Shi, Q., Hertogh, M., Bosch-Rekveldt, M., Zhu, J. and Sheng, Z. (2020), “Exploring decision-making Complexity in major infrastructure projects: a case study from China”, Project Management Journal, Vol. 51 No. 6, pp. 617-632, doi: 10.1177/8756972820919205.
Silvius, A.J.G., Kampinga, M., Paniagua, S. and Mooi, H. (2017), “Considering sustainability in project management decision making: an investigation using Q-methodology”, International Journal of Project Management, Vol. 35 No. 6, pp. 1133-1150, doi: 10.1016/j.ijproman.2017.01.011.
Smith, D.C., Dombo, H. and Nkehli, N. (2008), “‘Benefits realisation management in information technology projects’”, International Conference on Management of Engineering & Technology, 2008, PICMET 2008. Portland, pp. 1442-1455, doi: 10.1109/picmet.2008.4599758.
Stingl, V. and Geraldi, J. (2017), “Errors, lies and misunderstandings: systematic review on behavioural decision making in projects”, International Journal of Project Management, Vol. 35 No. 2, pp. 121-135, doi: 10.1016/j.ijproman.2016.10.009.
Svejvig, P. and Schlichter, B.R. (2020), “The long road to benefits management: toward an integrative management model”, Project Management Journal, Vol. 51 No. 3, pp. 312-327, doi: 10.1177/8756972819896485.
Thesing, T., Feldmann, C. and Burchardt, M. (2021), “Agile versus waterfall project management: decision model for selecting the appropriate approach to a project”, Procedia Computer Science, Vol. 181, pp. 746-756, doi: 10.1016/j.procs.2021.01.227.
Thoma, J. (2021), “Judgementalism about normative decision theory”, Synthese, Vol. 198 No. 7, pp. 6767-6787, doi: 10.1007/s11229-019-02487-0.
Toole, T.M. (2005), “A project management causal loop diagram”, 21st Annual ARCOM Conference, London, United Kingdom, available at: https://www.egr.msu.edu/classes/egr410/chalou/Toole%20PM%20Causal%20Loop%20Diagram.pdf
Turetken, O., Stojanov, I. and Trienekens, J.J.M. (2017), “Assessing the adoption level of scaled agile development: a maturity model for Scaled Agile Framework”, Journal of Software: Evolution and Process, Vol. 29 No. 6, pp. 1-18, doi: 10.1002/smr.1796.
Turner, R. (2020), “How does governance influence decision making on projects and in project-based organizations?”, Project Management Journal, Vol. 51 No. 6, pp. 670-684, doi: 10.1177/8756972820939769.
Turner, J.R. (2021), “Emotion regulation during decision making on projects”, Project Leadership and Society, Vol. 2, 100035, doi: 10.1016/j.plas.2021.100035.
ul Musawir, A., Serra, C.E.M., Zwikael, O. and Ali, I. (2017), “Project governance, benefit management, and project success: towards a framework for supporting organizational strategy implementation”, International Journal of Project Management, Vol. 35 No. 8, pp. 1658-1672, doi: 10.1016/j.ijproman.2017.07.007.
Van Staveren, I. (2007), “Beyond utilitarianism and deontology: ethics in economics”, Review of Political Economy, Vol. 19 No. 1, pp. 21-35, doi: 10.1080/09538250601080776.
VersionOne Inc (2020), “The 14th annual state of agile report”, available at: https://explore.digital.ai/state-of-agile/14th-annual-state-of-agile-report
Von Seggern, M. and Young, N.J. (2003), “The focus group method in libraries: issues relating to process and data analysis”, Reference Services Review, Vol. 31 No. 3, pp. 272-284, doi: 10.1108/00907320310486872.
Waters, S. (2020), Mill’s Utilitarianism and Kant’s Deontology: Comparing Two Heavyweights in Ethical Philosophy [Video File], YouTube, available at: https://www.youtube.com/watch?v=0zg3mzfuCks
White, M.D. (2009), “In defense of deontology and kant: a reply to van Staveren”, Review of Political Economy, Vol. 21 No. 2, pp. 299-307, doi: 10.1080/09538250902834103.
Williams, M. and Moser, T. (2019), “The art of coding and thematic exploration in qualitative research”, International Management Review, Vol. 15 No. 1, pp. 45-55, available at: http://americanscholarspress.us/journals/IMR/pdf/IMR-1-2019/IMR-v15n1art4.pdf
Yin, R.K. (2014), Case Study Research: Design and Methods, 5th ed., SAGE Publications, London.
Zarghami, S.A. and Zwikael, O. (2022), “Measuring project resilience – learning from the past to enhance decision making in the face of disruption”, Decision Support Systems, Vol. 160, pp. 1-12, doi: 10.1016/j.dss.2022.113831.
Zwikael, O. and Meredith, J.R. (2019), “Effective organizational support practices for setting target benefits in the project front end”, International Journal of Project Management, Vol. 37 No. 7, pp. 930-939, doi: 10.1016/j.ijproman.2019.08.001.
Zwikael, O., Meredith, J.R. and Smyrk, J. (2019), “The responsibilities of the project owner in benefits realization”, International Journal of Operations and Production Management, Vol. 39 No. 4, pp. 503-524, doi: 10.1108/IJOPM-02-2018-0086.