Causes of government construction projects failure in an emerging economy: Evidence from Ghana
International Journal of Managing Projects in Business
ISSN: 1753-8378
Article publication date: 23 April 2018
Issue publication date: 17 May 2018
Abstract
Purpose
The purpose of this paper is to investigate the factors that cause government construction projects failure in a developing economy.
Design/methodology/approach
The study used the sequential data collection approach through an in-depth semi-structured interview (16 participants) and questionnaire survey (230 participants) to solicit their perceptions from project management practitioners (PMP), contractors and client (government officials) about the factors that lead to Ghanaian Government construction projects. The relative importance index was used to determine the relative importance of the factors identified. This was followed by Spearman rank correlation coefficient and Kendall’s coefficient of concordance to measure the degree of agreement among the participants on their perceptions.
Findings
In total, 34 factors were identified as the main factors that lead into Ghanaian Government construction projects failure. The top ten most important factors that cause Ghanaian Government construction projects failure are: political interferences, delays in payment, partisan politics, bureaucracy, corruption, poor supervision, lack of commitment by project leaders, poor planning, starting more projects than the government can fund and change in government. The failure factors were grouped into four main themes and found that the most important failure factors are leadership. This is followed by management and administrative practices, resources and external forces, respectively.
Research limitations/implications
This study is limited to only the public sector, and therefore the findings may not be applicable in the private sector.
Practical implications
Policy makers and construction PMP would be able to use the findings as a guide during the implementation of government projects in order to reduce and/or avoid government construction projects failure.
Originality/value
Construction projects failure in developing countries is high. Accordingly, the extant literature has been devoted to identifying the factors that lead to failure; however, they have mainly been discussed from a generic point of view or individual case studies. Researches that focus exclusively on government construction projects in developing countries are rare despite the dynamics in which these projects are implemented. This research extends the construction project management literature by focussing on government construction projects in a developing economy, where there are weak public institutional systems coupled with partisanship politics and bad cultural orientation towards government sector work inherited from a colonial rule.
Keywords
Citation
Damoah, I.S. and Kumi, D.K. (2018), "Causes of government construction projects failure in an emerging economy: Evidence from Ghana", International Journal of Managing Projects in Business, Vol. 11 No. 3, pp. 558-582. https://doi.org/10.1108/IJMPB-04-2017-0042
Publisher
:Emerald Publishing Limited
Copyright © 2018, Emerald Publishing Limited