Omid Kebriyaii, Ali Heidari, Mohammad Khalilzadeh and Dragan Pamucar
Integrating project scheduling and material ordering problems is vital in realistically estimating project cost and duration. Also, the quality level of materials is important as…
Abstract
Purpose
Integrating project scheduling and material ordering problems is vital in realistically estimating project cost and duration. Also, the quality level of materials is important as one of the key project success factors.
Design/methodology/approach
In this paper, a three-objective mathematical model is presented for green project scheduling with materials ordering problems considering rental resources. The first objective is to minimize the total cost of the project site and logistics. The second objective is to minimize the environmental impacts of producing materials and the third objective is to maximize the total quality of materials. Since costs trigger several challenges in projects, cost constraints are considered in this model for the first time and also the cost of delay in supplying of materials by the suppliers has been deducted from the project costs. Subsequently, the model was implemented in a real case and solved by the Lagrangian Relaxation algorithm as an exact method on GAMS software for model validation.
Findings
Based on sensitivity analysis of some parameters, the findings indicate that the cost constraint and lead time have considerable effects on the project duration. Also, integrating project scheduling and material ordering improves the robustness of the project schedule.
Originality/value
The primary contributions of the present research can be stated as follows: considering the cost constraints in the project scheduling with material ordering problem, incorporating the rental resources and taking the quality levels of materials as well as the environmental impacts into account.
Details
Keywords
Mahendrawathi ER, Noval Arsad, Hanim Maria Astuti, Renny Pradina Kusumawardani and Rivia Atmajaningtyas Utami
The purpose of this paper is to present the result of using process mining to model the production planning (PP) process of a manufacturing company that is supported by enterprise…
Abstract
Purpose
The purpose of this paper is to present the result of using process mining to model the production planning (PP) process of a manufacturing company that is supported by enterprise resource planning (ERP) systems.
Design/methodology/approach
This paper uses event logs obtained from the case company’s ERP database. The steps for this research are planning process mining implementation, extraction and construction of event log, discovering process model with Heuristic Miner and analysis.
Findings
Process model obtained from process mining shows how the PP is actually conducted. It shows the loop in materials requirement planning and create plan order process. Furthermore, the occurrences of changing plan order date and production line indicate the schedule instability in the case company. Further analysis of the material management (MM) event log shows the implication of production plan changes on MM. Continuous change in the plan affects material allocation priority and may result in a mismatch between production needs and the materials available.
Research limitations/implications
The study is only conducted in a single and specific case. Therefore, even though the findings provide good insight, the use of solitary case study does not imply a general result applied to other cases. Hence, there is a need to conduct similar studies on various cases so that a more generic conclusion can be drawn.
Practical implications
The result provides insights into how the current company’s policy of adjusting the production plan to accommodate changing demand impacts their operation. It can help the company to consider a better balance between flexibility and efficiency to improve their process.
Originality/value
The paper demonstrates the use of process mining to capture the real progression of PP based on the data stored in the company’s ERP database, which give an insight into how a real company conducts their PP process, the implication of schedule instability on MM and production. The novelty of this research lies in the use of process mining to attest to the schedule nervousness issue at a process level.
Details
Keywords
Julija Moskvina, Anca Hanea, Tomas Vedlūga and Birutė Mockevičienė
This chapter discusses the empirical data analysis that will form the basis of the early pricing framework. It focusses on the complexity of furniture production and describes the…
Abstract
This chapter discusses the empirical data analysis that will form the basis of the early pricing framework. It focusses on the complexity of furniture production and describes the historical production data collected from companies, along with the potential applications of machine learning for knowledge management purposes. The chapter then presents the results of machine learning for early cost estimation as part of a lean innovation that is affordable and accessible for small and medium-sized enterprises (SMEs). Finally, the chapter describes an experiment on the structured expert evaluation methodology, which shows that a well-formed panel of experts can increase the predictive power of machine learning solutions, particularly at extreme points.
Details
Keywords
Richard A. Lancioni and James Palmquist
The classical definition of PDM focuses on the broad spectrum of distribution activity, from the inbound raw materials; to the finished product flow; and to the end user. The…
Abstract
The classical definition of PDM focuses on the broad spectrum of distribution activity, from the inbound raw materials; to the finished product flow; and to the end user. The definition is often stated as “all of the activities involved in the flow of goods from the manufacturer to the consumer which include inventory control, transportation, warehousing, order processing, materials management, and purchasing”. But despite the broad view described in the definition, little attention is given to the raw materials flow and to the entire area of Materials Management. Physical Distribution managers tend to disregard the inbound flow and regard it as the responsibility of some other management group in the company, specifically purchasing and/or production. The need for a well co‐ordinated and efficient distribution system demands that the PD manager pay more attention to the inbound material flow. The outcome of the decisions that a PD manager makes depends to a great degree on how well materials management and PDM are co‐ordinated in a firm:
Hessa Almatroushi, Moncer Hariga, Rami As'ad and AbdulRahman Al-Bar
This paper proposes an integrated approach that seeks to jointly optimize project scheduling and material lot sizing decisions for time-constrained project scheduling problems.
Abstract
Purpose
This paper proposes an integrated approach that seeks to jointly optimize project scheduling and material lot sizing decisions for time-constrained project scheduling problems.
Design/methodology/approach
A mixed integer linear programming model is devised, which utilizes the splitting of noncritical activities as a mean toward leveling the renewable resources. The developed model minimizes renewable resources leveling costs along with consumable resources related costs, and it is solved using IBM ILOG CPLEX optimization package. A hybrid metaheuristic procedure is also proposed to efficiently solve the model for larger projects with complex networks structure.
Findings
The results confirmed the significance of the integrated approach as both the project schedule and the material ordering policy turned out to be different once compared to the sequential approach under same parameter settings. Furthermore, the integrated approach resulted in substantial total costs reduction for low values of the acquiring and releasing costs of the renewable resources. Computational experiments conducted over 240 test instances of various sizes, and complexities illustrate the efficiency of the proposed metaheuristic approach as it yields solutions that are on average 1.14% away from the optimal ones.
Practical implications
This work highlights the necessity of having project managers address project scheduling and materials lot sizing decisions concurrently, rather than sequentially, to better level resources and minimize materials related costs. Significant cost savings were generated through the developed model despite the use of a small-scale example which illustrates the great potential that the integrated approach has in real life projects. For real life projects with complex network topology, practitioners are advised to make use of the developed metaheuristic procedure due to its superior time efficiency as compared to exact solution methods.
Originality/value
The sequential approach, wherein a project schedule is established first followed by allocating the needed resources, is proven to yield a nonoptimized project schedule and materials ordering policy, leading to an increase in the project's total cost. The integrated approach proposed hereafter optimizes both decisions at once ensuring the timely completion of the project at the least possible cost. The proposed metaheuristic approach provides a viable alternative to exact solution methods especially for larger projects.
Details
Keywords
Patrik Jonsson and Stig‐Arne Mattsson
The paper seeks to describe the state‐of‐the‐art, reasons for selecting various material planning methods, and modes of applying methods for initiating inventory replenishment of…
Abstract
Purpose
The paper seeks to describe the state‐of‐the‐art, reasons for selecting various material planning methods, and modes of applying methods for initiating inventory replenishment of purchased items. It also identifies trends from 1993 to 2005.
Design/methodology/approach
Empirical survey data are collected from Swedish manufacturing companies in 1993, 1999 and 2005. The MRP, re‐order point, fixed interval ordering, run‐out time, and Kanban methods are studied.
Findings
MRP is the most commonly used method and its position has strengthened since 1993. A common way of determining parameters such as order quantities and safety stocks is to use judgment and experience. Parameters used in material planning methods are reviewed relatively infrequently. The planning frequency has increased, with daily planning now being typical.
Research limitations/implications
The major limitation is that different data collection techniques were used in 1993 compared with 1999 and 2005. An important research implication is that the state‐of‐the‐art applications differ from theoretically appropriate application modes. The trends are towards less appropriate modes among the most widespread applications.
Practical implications
The frequency of reviewing planning variables is relatively low in industry, and should in most situations be increased. The paper implies that more user‐friendly software applications need to be developed and implemented. It could serve as guidelines when designing and developing training and education programs and function as a benchmark.
Originality/value
The paper provides a longitudinal state‐of‐the‐art description of materials planning usage and identifies application modes with positive and negative performance impact.
Details
Keywords
The objective of this study is to investigate how country risk, different political actions from the government and bureaucratic behavior influence the activities in industry…
Abstract
The objective of this study is to investigate how country risk, different political actions from the government and bureaucratic behavior influence the activities in industry supply chains (SCs) in emerging markets. The main objective of this study is to investigate the influence of these external stakeholders’ elements to the demand-side and supply-side drivers and barriers for improving competitiveness of Ready-Made Garment (RMG) industry in the way of analyzing supply chain. Considering the phenomenon of recent change in the RMG business environment and the competitiveness issues this study uses the principles of stakeholder and resource dependence theory and aims to find out some factors which influence to make an efficient supply chain for improving competitiveness. The RMG industry of Bangladesh is the case application of this study. Following a positivist paradigm, this study adopts a two phase sequential mixed-method research design consisting of qualitative and quantitative approaches. A tentative research model is developed first based on extensive literature review. Qualitative field study is then carried out to fine tune the initial research model. Findings from the qualitative method are also used to develop measures and instruments for the next phase of quantitative method. A survey is carried out with sample of top and middle level executives of different garment companies of Dhaka city in Bangladesh and the collected quantitative data are analyzed by partial least square-based structural equation modeling. The findings support eight hypotheses. From the analysis the external stakeholders’ elements like bureaucratic behavior and country risk have significant influence to the barriers. From the internal stakeholders’ point of view the manufacturers’ and buyers’ drivers have significant influence on the competitiveness. Therefore, stakeholders need to take proper action to reduce the barriers and increase the drivers, as the drivers have positive influence to improve competitiveness.
This study has both theoretical and practical contributions. This study represents an important contribution to the theory by integrating two theoretical perceptions to identify factors of the RMG industry’s SC that affect the competitiveness of the RMG industry. This research study contributes to the understanding of both external and internal stakeholders of national and international perspectives in the RMG (textile and clothing) business. It combines the insights of stakeholder and resource dependence theories along with the concept of the SC in improving effectiveness. In a practical sense, this study certainly contributes to the Bangladeshi RMG industry. In accordance with the desire of the RMG manufacturers, the research has shown that some influential constructs of the RMG industry’s SC affect the competitiveness of the RMG industry. The outcome of the study is useful for various stakeholders of the Bangladeshi RMG industry sector ranging from the government to various private organizations. The applications of this study are extendable through further adaptation in other industries and various geographic contexts.
Details
Keywords
Considerable effort is needed to design the software and the material‐flow system to meet the needs of manufacturing which is driven by customer demand. Top management initiative…
Abstract
Considerable effort is needed to design the software and the material‐flow system to meet the needs of manufacturing which is driven by customer demand. Top management initiative and support is required throughout. Here, Prof. Dr. Sankaran describes the concept developed by Siemens in two major projects.
Many manufacturing organizations are switching over to JITmanufacturing systems following the success of Japanese industries.Presents a case study of a simulation modelling…
Abstract
Many manufacturing organizations are switching over to JIT manufacturing systems following the success of Japanese industries. Presents a case study of a simulation modelling approach in the design and analysis of a proposed JIT system for an Australian chemical company, which currently operates on a traditional system. The approach was used to compare two cell designs, and to estimate utilization levels for operators and materials handlers under the new system, and to determine reorder levels for raw materials at the work stations in order to operate the JIT system successfully.