1 – 10 of 97Abraham Assefa Tsehayae and Aminah Robinson Fayek
Despite long-term, sustained research and industry practice, predicting construction labour productivity (CLP) using existing factor and activity modelling approaches remains a…
Abstract
Purpose
Despite long-term, sustained research and industry practice, predicting construction labour productivity (CLP) using existing factor and activity modelling approaches remains a challenge. The purpose of this paper is to first demonstrate the limited usefulness of activity models and then to propose a system model approach that integrates factor and activity models for better prediction of CLP.
Design/methodology/approach
The system model parameters – comprising factors and practices – and work sampling proportions (WSPs) were identified from literature. Field data were collected from 11 projects over a span of 29 months. Activity models based on the relationship between CLP and WSPs were created, and their validity was tested using regression analysis for eight activities in the concreting, electrical and shutdown categories. The proposed system model was developed for concreting activity using the key influencing parameters in conjunction with WSPs.
Findings
The results of the regression analysis indicate that WSPs, like direct work, are not significantly correlated to CLP and fail to explain its variance. Evaluation of the system model approach for the concreting activity showed improved CLP prediction as compared to existing approaches.
Research limitations/implications
The system model was tested for concreting activity using data collected from six projects; however, further investigation into the model’s accuracy and efficacy using data collected from other labour-intensive activities is suggested.
Originality/value
This research establishes the role of WSPs in CLP modelling, and develops a system modelling approach to assist researchers and practitioners in the analysis of productivity-influencing parameters together with WSPs.
Details
Keywords
U.D.R.E. Ruwanpura, B.A.K.S. Perera and Tharusha Ranadewa
Administrative processes play a crucial role in various sectors, often contributing to cost overruns and delays. While lean concept has been extensively applied in many…
Abstract
Purpose
Administrative processes play a crucial role in various sectors, often contributing to cost overruns and delays. While lean concept has been extensively applied in many industries, there is a recognized need for further research on the integration of lean in administrative processes. To address this research gap, this study aims to systematically analyse the implementation of lean in administrative processes, providing a sector-wise comparison to explore its prospects for the construction industry.
Design/methodology/approach
A systematic literature review was conducted by adapting the Preferred Reporting Items for Systematic Reviews and Meta-Analyses method. Eighty-six research papers are subjected to descriptive and content analysis on different tools applied in lean integrated administrative processes in health care, education, public administration and other sectors.
Findings
The research study reveals common lean tools irrespective of sector. Moreover, specific tools used for a particular sector are analysed. Out of the various lean tools and techniques, value stream mapping, 5S and Kaizen are highly acknowledged tools in every sector of lean intervention. Furthermore, ECRS is applied explicitly in the education sector. Furthermore, it is noted that Suppliers, Inputs, Process, Outputs and Customers (SIPOC), 5whys, load levelling and control charts are identical to administrative processes in lean health care. Furthermore, Spaghetti charts and Kaikaku are only adapted to administrative processes in the public administration sector, and causal loop diagrams are used explicitly in administrative processes in the construction sector.
Originality/value
This study contributes to research by developing a guideline to design lean intervention for a lean-integrated administrative process in any sector which still needs to be transformed into lean. Hence, this study will be a cornerstone for incorporating lean principles for administrative processes in construction sector.
Details
Keywords
U.D.R.E. Ruwanpura and B.A.K.S. Perera
Accelerating the influences of external stakeholders in any construction project is inevitable. Studies on external stakeholder influence on construction projects and literature…
Abstract
Purpose
Accelerating the influences of external stakeholders in any construction project is inevitable. Studies on external stakeholder influence on construction projects and literature on external stakeholder management in irrigation infrastructure projects executed with donor funds are scarce. Thus, this study aimed to investigate how to manage the external stakeholders' influence on donor-funded irrigation infrastructure projects effectively.
Design/methodology/approach
A mixed approach consisting of 17 semi-structured interviews and two rounds of questionnaire surveys was adopted to rank the following: the types of external stakeholders who can significantly influence irrigation infrastructure projects, significant influencing strategies used by those stakeholders, and significant strategies that can be adopted to manage external stakeholder influence on the projects.
Findings
In total, 12 of external stakeholders who can significantly influence irrigation infrastructure projects were identified; 17 significant influencing strategies used by external project stakeholders and 22 significant strategies used to manage external stakeholder influence on the projects were identified. The influencing/management strategies specific to each external stakeholder type and those that are common to all external stakeholder types were identified separately. The grievance redress mechanism should be activated for managing external stakeholder influence on donor-funded irrigation infrastructure projects.
Originality/value
This study contributes to theory by identifying significant strategies that can be used to manage external stakeholder influence on donor-funded irrigation infrastructure projects during the planning and design stages. The study will help project teams to handle external stakeholder influence on the projects successfully, accomplish project objectives, and make maximum utilization of the donor funds received.
Details
Keywords
John E. McDonnell, Helle Abelvik-Lawson and Damien Short
This chapter discusses the role of energy production in the global capitalist economy and its relationship to the Sustainable Development Goals (SDGs), with particular focus on…
Abstract
This chapter discusses the role of energy production in the global capitalist economy and its relationship to the Sustainable Development Goals (SDGs), with particular focus on SDG 8 – ‘Promote sustained, inclusive and sustainable economic growth, full and productive employment and decent work for all’ – and SDG 12 – ‘Ensure sustainable consumption and production patterns’. It achieves this by first introducing the Club of Rome report the Limits to Growth which utilised a system dynamics computer model to simulate the interactions of five global economic subsystems (population, food production, industrial production, pollution and consumption of nonrenewable natural resources) (Meadows, Meadows, Randers, & Behrens III, 1972), the results of which posed serious challenges for global sustainability, to better understand and contextualise unconventional (also referred to as ‘extreme’) and ‘renewable’ energy production as examples of the paradoxical nature of sustainable development in the global capitalist economy. Demonstrating that unconventional energy production methods are much less efficient, more carbon intensive, more environmentally destructive and just as unsustainable, and that renewable energy relies on the extraction of nonrenewable natural resources such as lithium that result in similar environmental and social issues, this chapter will interrogate this and ask the question – is the capitalist system in its current form capable of making ‘sustainable development something more than the oxymoron it appears?’.
Details
Keywords
Citra S. Ongkowijoyo, Argaw Gurmu and Andi Andi
The complexities in strait-crossing cable-stayed bridge project are increasing the risks. This study aims to identify and analyze the significant and worth-considered construction…
Abstract
Purpose
The complexities in strait-crossing cable-stayed bridge project are increasing the risks. This study aims to identify and analyze the significant and worth-considered construction risks of the first, biggest and longest spanned strait-crossing bridge project in Indonesia.
Design/methodology/approach
As many as 32 risk events were identified and determined as the risks that exist and can be represented in the Suramadu bridge project context. Data was collected through a design-based questionnaire disseminated to experts involved in the project as well as semi-formal interviews. Several quantitative methods were applied to analyze the significant risks, such as relative importance index, Spearman’s rank correlation test and Mann–Whitney U test.
Findings
The analyses reveal that “unexpected natural behavior” confirmed by both contractor and consultant parties is the most significant and crucial risk event. Another risk event found to be significant is the “delayed payment.” On the other hand, it is also found that several risks within the legal category are found to be less significant compared to other major risk events.
Research limitations/implications
The results of the present research should be interpreted in the context of several limitations. Given these possible concerns regarding the generalizability of the findings, along with the relatively low rate of participants in the current research, additional studies are needed to provide a more complete picture of stakeholder perceptions who are involved directly in the construction environment as well as to identify more construction risks specifically in the large-scale bridge project.
Practical implications
This study has provided fundamental contributions to the body of knowledge and practical implication to promote and assist decision-makers toward developing a comprehensive risk assessment of a large-scale bridge project.
Originality/value
The analyses of outcomes and discussion, as well as the findings of this research, have shed light on the construction risks understanding, which contributes to delivering a theoretical framework for achieving large-scale bridge project success.
Details
Keywords
Pouyan Mahdavi-Roshan and Seyed Meysam Mousavi
Most projects are facing delays, and accelerating the pace of project progress is a necessity. Project managers are responsible for completing the project on time with minimum…
Abstract
Purpose
Most projects are facing delays, and accelerating the pace of project progress is a necessity. Project managers are responsible for completing the project on time with minimum cost and with maximum quality. This study provides a trade-off between time, cost, and quality objectives to optimize project scheduling.
Design/methodology/approach
The current paper presents a new resource-constrained multi-mode time–cost–quality trade-off project scheduling model with lags under finish-to-start relations. To be more realistic, crashing and overlapping techniques are utilized. To handle uncertainty, which is a source of project complexity, interval-valued fuzzy sets are adopted on several parameters. In addition, a new hybrid solution approach is developed to cope with interval-valued fuzzy mathematical model that is based on different alpha-levels and compensatory methods. To find the compatible solution among conflicting objectives, an arithmetical average method is provided as a compensatory approach.
Findings
The interval-valued fuzzy sets approach proposed in this paper is denoted to be scalable, efficient, generalizable and practical in project environments. The results demonstrated that the crashing and overlapping techniques improve time–cost–quality trade-off project scheduling model. Also, interval-valued fuzzy sets can properly manage expressions of the uncertainty of projects which are realistic and practical. The proposed mathematical model is validated by solving a medium-sized dataset an adopted case study. In addition, with a sensitivity analysis approach, the solutions are compared and the model performance is confirmed.
Originality/value
This paper introduces a new continuous-based, resource-constrained, and multi-mode model with crashing and overlapping techniques simultaneously. In addition, a new hybrid compensatory solution approach is extended based on different alpha-levels to handle interval-valued fuzzy multi-objective mathematical model of project scheduling with influential uncertain parameters.
Details
Keywords
Mershack Opoku Tetteh, Albert P.C. Chan, Amos Darko, Beliz Özorhon and Emmanuel Adinyira
International construction joint ventures (ICJVs) will fully realize their potential for success and effectively monitor performance when an adequate and suitable performance…
Abstract
Purpose
International construction joint ventures (ICJVs) will fully realize their potential for success and effectively monitor performance when an adequate and suitable performance benchmark is established. However, existing studies fall short of adequately providing a mutually acceptable benchmark for assessing the performance of ICJVs. This study aims to develop an adequate and suitable performance measurement framework for ICJVs.
Design/methodology/approach
A twofold structured questionnaire survey, supplemented by semi-structured interviews, was used to collect data from the practitioners of ICJVs hosted in the developing country of Ghana. The data were analyzed by using descriptive statistics, confirmatory factor analysis (CFA) and a hybrid-fuzzy logic approach.
Findings
A list of 30 performance indicators (PIs), defined by project performance, perceived satisfaction, company/partner performance, socio-environmental performance and performance of ICJV management, was validated and proved to be significant. Only 22 out of the 30 PIs, focusing on project efficiency, societal improvement and organizational goals are realized by the ICJV practitioners. Further, suitable determinants and viable quantitative ranges for measuring each PI are established to prevent different interpretations of the meanings of PIs and objectively express the level of success in quantitative terms. The results call for further investigation of the convergence between the practice of and research into some PIs (e.g. socio-environmental performance) and a range of different performance levels (PLs) in a more scientific manner.
Practical implications
This study not only advances the knowledge base and practice of performance measurement in ICJVs but could also assist stakeholders and decision-makers to assess, compare and monitor the performance of different ICJV projects on common grounds objectively.
Originality/value
This study not only comprehensively assessed PIs – what to measure – but also systematically determined suitable determinants – how to measure – for each PI.
Details
Keywords
Mershack Opoku Tetteh, Albert P.C. Chan, Amos Darko, Sitsofe Kwame Yevu, Emmanuel B. Boateng and Janet Mayowa Nwaogu
International construction joint ventures (ICJVs) are an effective strategy for construction companies worldwide for delivering large and complex projects. Despite numerous ICJVs…
Abstract
Purpose
International construction joint ventures (ICJVs) are an effective strategy for construction companies worldwide for delivering large and complex projects. Despite numerous ICJVs studies, there is a lack of comprehensive empirical examination of what drives ICJVs implementation. This study aims to investigate the key drivers for implementing ICJVs through an international survey.
Design/methodology/approach
Grounded on a comprehensive literature review and structured questionnaire survey, 123 ICJV experts' responses from 24 different countries/jurisdictions were analyzed using inferential and descriptive statistics. Mann–Whitney U test was used to determine any divergence of ranking of the drivers by the experts. Factor analysis (FA) was used to identify the clusters underlying the key drivers. Rank agreement analysis was later used to investigate the consensus between experts from developing and developed countries/jurisdictions on their ranking of the clusters.
Findings
Out of 34 factors, 26 factors greatly drive the implementation of ICJVs. Mann–Whitney U test results prove the absence of significant disparity among the experts in the ranking of the drivers. Six clusters were obtained through factor analysis (FA), namely, market-penetration and innovation-driven drivers, legal and market-driven drivers, fiscal incentives and market expansion drivers, personal branding drivers, sustainable advantage/power drivers and industrial and organizational promotion drivers. Rank agreement analysis exhibited varied levels of concurrence between professionals from developed and developing countries/jurisdictions.
Practical implications
The appreciation of the factors motivating ICJVs is beneficial to the successful implementation of ICJV strategies. A clear understanding of the drivers can help practitioners and policymakers to customize their ICJVs to reap the expected benefits.
Originality/value
The study has generated valuable insights into the factors that are greatly driving the implementation of ICJVs worldwide. While the findings of this study provide a profound contribution to theory and practice, it contributes to sustainable growth in different perspectives.