1 – 10 of 69Robert Osei-Kyei, Albert P.C. Chan, Yu Yao and Khwaja Mateen Mazher
Conflict between project parties is among the major risk factors in public–private partnership (PPP) in developing countries that has, in extreme cases, led to the failure or…
Abstract
Purpose
Conflict between project parties is among the major risk factors in public–private partnership (PPP) in developing countries that has, in extreme cases, led to the failure or distress of many PPP projects. This paper aims to explore conflict prevention measures for PPPs in developing countries using Ghana as a case study.
Design/methodology/approach
From a comprehensive review of literature, a list of conflict prevention measures was derived; further, a questionnaire survey was conducted with PPP experts from Ghana. Kendall’s coefficient of concordance test, range normalization method and factor analysis were used for data analysis.
Findings
Results show four significant conflict prevention measures for PPPs in developing countries, they include extensive stakeholder consultation in decision makings, clear goals and mutual benefit objectives, clarity of roles and responsibilities of parties and transparent appeal procedures. Using the factor analysis technique, the prevention measures are grouped into three unrelated categories, they are efficient communication structure and risk assessments, transparency and openness and proficient service delivery.
Originality/value
The research findings inform policymakers and local practitioners of the strategic measures and procedures needed to minimize the occurrence of conflicts in PPPs in developing countries.
Details
Keywords
Robert Osei-Kyei and Albert P.C. Chan
Since 1960, many public–private partnership (PPP) projects have been implemented in Hong Kong. Some projects have been considered as very successful, whereas others are seen as…
Abstract
Purpose
Since 1960, many public–private partnership (PPP) projects have been implemented in Hong Kong. Some projects have been considered as very successful, whereas others are seen as less successful. Unfortunately, these success outcomes have remained abstract because they are not in quantifiable terms. This paper aims to develop a model that can quantify the success outcome of PPP projects in Hong Kong.
Design/methodology/approach
Both quantitative and qualitative research approaches were adopted for the study. First, a questionnaire survey was conducted with PPP practitioners in Hong Kong, and thereafter, the fuzzy synthetic evaluation technique was used to develop a project success index for PPP projects in Hong Kong. The Hong Kong Cross-Harbour Tunnel project was used as a case study to demonstrate the applicability of the pragmatic model.
Findings
The success index model developed consists of four unrelated success criteria groupings: cost effectiveness, quality of services and technical specification, environmental impact and long-term partnership. Further, the computed success index for the Cross-Harbour Tunnel project is 4.06, which indicates that the tunnel project has been highly successful.
Originality/value
The outputs of this study will enable PPP practitioners in Hong Kong to reliably evaluate the success levels of their projects. In addition, local practitioners can now compare the success levels of two or more PPP projects on the same basis.
Details
Keywords
Robert Osei-Kyei and Albert P.C. Chan
The purpose of this paper is to empirically compare the risk factors in public-private partnership (PPP) projects in developing and developed countries, represented by Ghana and…
Abstract
Purpose
The purpose of this paper is to empirically compare the risk factors in public-private partnership (PPP) projects in developing and developed countries, represented by Ghana and Hong Kong, respectively.
Design/methodology/approach
A structured questionnaire survey was conducted with PPP practitioners in Ghana and Hong Kong. In total, 103 valid responses were received for analysis. Kendall’s coefficient of concordance and mean ranking were used for data analysis.
Findings
The results show that respondents from Ghana ranked country risk factors higher, whereas their Hong Kong counterparts ranked project-specific risks higher. The top five significant risks in Ghana are corruption, inflation rate fluctuation, exchange rate fluctuation, delay in project completion and interest rate fluctuation. In Hong Kong, the top five significant risk factors are delay in land acquisition, operational cost overruns, construction cost overruns, delay in project completion and political interference.
Originality/value
The results of the study inform international investors of the appropriate risk mitigation measures and preventive actions to use when engaging in PPP arrangements in any part of the world. Further, governments who are yet to use the PPP concept would be informed of the prevailing risk factors in other neighbouring countries (i.e. developing or developed countries).
Details
Keywords
Robert Osei-Kyei, Timur Narbaev, Michael Atafo-Adabre, Nicholas Chileshe and Joseph Kwame Ofori-Kuragu
The demand for retirement villages globally has been increasing due to the rapid growth in the ageing population in recent years. To address the rising challenges in the…
Abstract
Purpose
The demand for retirement villages globally has been increasing due to the rapid growth in the ageing population in recent years. To address the rising challenges in the retirement market, the public–private partnership (PPP) has become a feasible method to develop retirement villages. This paper aims to survey and examine the key success criteria (SC) for using the PPP approach in the retirement village sector.
Design/methodology/approach
An empirical questionnaire survey was conducted with experts experienced in international PPP and retirement village. The analysis was conducted using one-way analysis of variance, mean score analysis, Kendall’s coefficient of concordance and factor analysis.
Findings
Results indicate that out of the 16 recognized SC, the most significant ones are SC1: “Affordability”, SC11: “Reduced social isolation of residents” and SC14: “Improvement of emotional wellbeing of residents”. Furthermore, results from the factor analysis technique indicate that the 16 SC can be classified into five major factor groupings, and these include SCG1 – “Financial performance of project”; SCG2 – “Adherence to design and technical specifications”; SCG3 – “Adherence to local council/authority’s environmental health and socio-economic requirements”; SCG4 – “Social inclusion and risk management”; and SCG5 – “Advancement in emotional wellbeing and physical health of residents”.
Originality/value
The study will sufficiently assist retirement village stakeholders, retirement village project participants and related government authorities of the best measures to put in place to maintain the sustainable development of the global retirement village market.
Details
Keywords
Robert Osei-Kyei and Albert P.C. Chan
This paper aims to empirically investigate the differences and similarities on the implementation constraints in public–private partnership (PPP) in developing and developed…
Abstract
Purpose
This paper aims to empirically investigate the differences and similarities on the implementation constraints in public–private partnership (PPP) in developing and developed economies/countries, represented by Ghana and Hong Kong, respectively.
Design/methodology/approach
A questionnaire survey was conducted with relevant experienced PPP practitioners in Ghana and Hong Kong. One hundred and three completed questionnaires were received for analysis. Kendall’s coefficient of concordance analysis, mean score ranking, Mann–Whitney U test and quartile grouping were used for data analysis.
Findings
The results show six implementation constraints with significant differences. Constraints related to the general investment climate of PPP projects (i.e. ecological conditions of PPP) are ranked higher in Ghana than in Hong Kong, whereas constraints related to the organisation and negotiations of PPP projects are higher in Hong Kong than in Ghana. Further, two constraints, lengthy delay in finalising negotiations and lengthy delay due to political debate, are very critical in both jurisdictions, whereas “negative public perceptions on PPP transactions” and “high use of unsolicited proposals” are of less challenge in the implementation of PPP in both jurisdictions.
Originality/value
The findings of this study contribute to knowledge on the international best practices of PPP. In addition, international private bidders would be informed of the mitigation measures to adopt when engaging in PPP arrangements in any part of the world, whether in a developing or developed economy country.
Details
Keywords
Ibrahim Yahaya Wuni, Geoffrey Qiping Shen and Robert Osei-Kyei
Prefabricated prefinished volumetric construction (PPVC) is a game-changing construction method that transforms the fragmented site-based construction of buildings into an…
Abstract
Purpose
Prefabricated prefinished volumetric construction (PPVC) is a game-changing construction method that transforms the fragmented site-based construction of buildings into an integrated production, integration and assembly of value-added volumetric building components. Where circumstances merit, the effective implementation of PPVC leverages significant gains in time, cost, quality, productivity and sustainability performance of construction projects. As PPVC is increasingly becoming mainstream, it is imperative to identify the critical success criteria (CSC) for measuring PPVC project success. The purpose of this study is to identify, rank and benchmark the CSC for measuring PPVC project success.
Design/methodology/approach
This study adopted a quantitative research design where the potential CSC for PPVC projects were evaluated. A comprehensive literature and pilot expert review identified 18 CSC for measuring PPVC project success. Based on a questionnaire survey of international PPVC experts, the 18 CSC were analyzed and prioritized using mean score analysis and weighting function.
Findings
Based on mean index assessment, the top five CSC for PPVC projects were identified as adherence to project schedules, meeting project quality specification, meeting safety requirements, client and owner satisfaction and cost savings and profitability. Further analysis grouped the 18 CSC into six principal success criteria (PSC), comprising time performance, cost performance, quality performance, environmental and safety performance, stakeholder satisfaction and supply chain performance. Based on weighted analysis of the six PSCs, quality performance, time performance and environmental and safety performance obtained the highest weights.
Research limitations/implications
The research results are limited by the following limitations. First, although adequate, the sample size was relatively smaller. Second, the generalized analysis overlooked the geospatial sensitivities of the CSC.
Originality/value
The results constitute the first exclusive quantitative ranking and prioritization of the CSC for PPVC projects. The outputs of this study will enable practitioners to reliably and accurately evaluate the performance levels of PPVC projects. A framework of the CSC for measuring the success of PPVC projects was developed.
Details
Keywords
Robert Osei-Kyei and Albert P.C. Chan
The purpose of this paper is to investigate the similarities and differences of critical success factors (CSFs) for public-private partnership (PPP) projects in developing and…
Abstract
Purpose
The purpose of this paper is to investigate the similarities and differences of critical success factors (CSFs) for public-private partnership (PPP) projects in developing and developed countries, using Ghana and Hong Kong as examples.
Design/methodology/approach
An empirical questionnaire survey was conducted with experienced PPP practitioners in Ghana and Hong Kong. Survey responses were analysed using Kendall’s concordance analysis, mean score ranking, quartile groupings analysis and Mann-Whitney U test.
Findings
The results indicate that a favourable legal and regulatory framework is very critical in both jurisdictions. Further, technology transfer, technological innovation, public/community participation and coordination and government providing financial support are of low importance in both jurisdictions. The non-parametric test shows that 16 CSFs are of different importance in Ghana and Hong Kong. Specifically, CSFs related to the socio-political and economic conditions of PPP projects are very critical in Ghana, whereas CSFs directly related to the organisation and relationship of PPP projects are very critical in Hong Kong.
Originality/value
The outputs of this study add to the international best practice framework for successful PPP implementation. Further, international private investors and governments who are yet to adopt the PPP concept would be considerably informed of the investment strategies to employ when engaging in PPP arrangements.
Details
Keywords
Isaac Akomea-Frimpong, Xiaohua Jin, Robert Osei-Kyei and Augustine Senanu Kukah
The contribution of the public–private partnership (PPP) model towards the achievement of the United Nation (UN)'s Sustainable Development Goals (SDGs) has been widely…
Abstract
Purpose
The contribution of the public–private partnership (PPP) model towards the achievement of the United Nation (UN)'s Sustainable Development Goals (SDGs) has been widely acknowledged. However, limited studies have shed light on the connection between PPPs and the achievement of these coveted goals in Ghana. In this study, the authors aimed at analysing and synthesising the existing literature on the use of PPP to achieve sustainability in infrastructure projects in the country.
Design/methodology/approach
A three-step approach was used to retrieve and review 60 selected articles aided by content analysis.
Findings
The analysis showed that all existing relevant publications on the application of the PPP model to attain UN’s SDGs in the country are organised around dominant themes, such as poverty alleviation, urban development, waste management and risk management. However, the review revealed little studies exist on pertinent issues relating to PPPs and sustainable development goals, such as climate action, critical resilience, sustainable finance and clean energy.
Research limitations/implications
Although the study is limited to 60 articles in Ghana, the results reveal pertinent gaps for further research studies to achieve sustainable infrastructural development in Ghana and other countries.
Practical implications
Holistically, the outcome of this study will serve as a guide to project managers to understand essential issues on attaining sustainability on public projects.
Originality/value
This article contributes to the literature and practice on the significance of PPP in mainstreaming UN's SDGs in public infrastructure projects.
Details
Keywords
Robert Osei-Kyei and Albert P.C. Chan
The public sector plays a critical role in the successful implementation of public–private partnership (PPP) projects. Thus, there is a need to holistically explore the public…
Abstract
Purpose
The public sector plays a critical role in the successful implementation of public–private partnership (PPP) projects. Thus, there is a need to holistically explore the public sector’s view on the implementation practices of PPP. This paper aims to explore and compare the public sector’s views on PPP practices in Ghana and Hong Kong.
Design/methodology/approach
Semi-structured interviews were conducted with PPP practitioners of senior authority in public institutions in both Ghana and Hong Kong. The interviews covered critical issues of PPP implementation practices such as motivations for engaging in PPP, success criteria/indicators, critical success factors (CSFs), external stakeholder management and training and education in PPPs.
Findings
The findings show that quick delivery of public projects and private sector efficiency are the reasons considered by both groups of interviewees. On the success criteria, interviewees from both jurisdictions mentioned user satisfaction, budget, time and quality. The CSFs mentioned by both groups include capacity building and training, project viability, proper planning and good feasibility studies. Sensitization programs, including open forums and community meetings, were mentioned by both groups as measures for managing external stakeholders. On the training and education, both groups mentioned international study tours and organizing courses and seminars.
Originality/value
The outputs of this study offer strategies that are very useful to international private developers who are interested in PPP practices in Africa and Asia. Further, the findings contribute to the knowledge on the international best practices for PPP.
Details
Keywords
Robert Osei-Kyei, Albert P.C. Chan and Ernest Effah Ameyaw
The purpose of this paper is to identify the factor groupings of a set of 19 critical success factors (CSFs) associated with managing public-private partnership (PPP) projects at…
Abstract
Purpose
The purpose of this paper is to identify the factor groupings of a set of 19 critical success factors (CSFs) associated with managing public-private partnership (PPP) projects at the operational stage and examine the most significant factor grouping using fuzzy synthetic evaluation (FSE) technique.
Design/methodology/approach
The paper adopted a comprehensive review of the pertinent literature and an empirical questionnaire survey geared towards targeted international PPP experts. Survey responses were analysed using factor analysis and FSE modelling.
Findings
The results from factor analysis show five CSF groupings (CSFGs) for managing operational PPPs. These are proficient service delivery and adequate legal structures, simplified payment mechanism and consistent project monitoring, effective contract variations management, suitable stakeholder management mechanism and environmental health and safety control. The FSE modelling shows that “simplified payment mechanism and consistent project monitoring”, is the most critical CSFG. The operational management CSFs under this grouping are acceptable level of user fee charges, efficient and well-structured payment mechanism, consistent project performance monitoring and long-term demand for public facility.
Research limitations/implications
The major limitation lies in the low sample size that was used for analysis; however the years of research and/or industrial experience of respondents and the wide coverage of different cultural backgrounds (18 countries from five regions globally) contribute to the authenticity of the survey responses. Future research should adopt interviews and case study analysis to unravel CSFs in managing operational PPPs.
Originality/value
The findings of this study are considerably beneficial to both public authorities and private operators. They inform practitioners of the strategic procedures and measures to employ in optimising the operational performance of PPP projects. Further, the methodology employed allows project management experts to reliably select the operational management CSFs for their projects.