Article
Publication date: 2 October 2017

Vahed Ghiasi, Ebrahim Kaivan, Nima Arzjani and Danial Arzjani

The purpose of this paper is to identify and prioritize the causes of delay in development projects and present strategies to reduce the delay.

1040

Abstract

Purpose

The purpose of this paper is to identify and prioritize the causes of delay in development projects and present strategies to reduce the delay.

Design/methodology/approach

The discussion includes the failure mode and effects analysis (FMEA) method for converting survey data, fuzzy risk priority number (FRPN) for prioritizing the delay factors, and the proposed solutions to reduce the delay of projects.

Findings

The research provided prioritized delay factors to show the importance of each delay factor in the projects by analyzing the survey data. Results show that lack of proper contract price to win the tender has the most impact on the delay of development project between delay factors.

Originality/value

This study offered some guidelines for people who are involved with contracts and development projects, so that they can use these suggestions to prevent possible factors that may cause delay in projects. This paper also demonstrated a process of analyzing the data which was provided by FMEA and FRPN methods.

Details

International Journal of Quality & Reliability Management, vol. 34 no. 9
Type: Research Article
ISSN: 0265-671X