Article
Publication date: 31 January 2023

Shuvo Dip Datta, Md. Habibur Rahman Sobuz, Mohammad Nafe Assafi, Norsuzailina Mohamed Sutan, Md. Nazrul Islam, Maria Binte Mannan, Abu Sayed Mohammad Akid and Noor Md. Sadiqul Hasan

This paper aims to identify the critical project management success factors and analyze those factors to achieve a sustainable construction industry in Bangladesh.

Abstract

Purpose

This paper aims to identify the critical project management success factors and analyze those factors to achieve a sustainable construction industry in Bangladesh.

Design/methodology/approach

This study identified 41 major problematic factors from the related literature. In this research, a detailed questionnaire survey was conducted among the experts and stakeholders of the construction industry of Bangladesh. The survey was carried out on a Likert scale and ranked the critical factors using the relative importance index (RII). The 41 problematic factors were divided into five group factors and ranked by the RII index to prioritize the factors. Finally, stakeholders' opinions were analyzed with the critical assessed factors, which was a very effective technique to eliminate the risks and uncertain occurrences in the construction industry of Bangladesh.

Findings

The factors analysis revealed that cost overrun, traffic jam, low wedges, slow payment for completed works and financial issues of the owner were leading critical factors in construction projects. Moreover, the critical factors are divided into five-factor groups, namely, financial management, monitoring and feedback, competency management, communication and coordination management, and risk management, which exhibit 0.767, 0.720, 0.711, 0.710 and 0.658 RII values. After all, the stakeholders' opinion suggested that implementing modern tools and techniques can help to avoid the critical situation in the construction industry of Bangladesh.

Practical implications

The construction industry of Bangladesh is moving away from stable construction work day by day. Previously, the potential CSFs were discussed unstructured way. Hence, detecting early warning signals in a structured way has become necessary for the building firm's survival.

Originality/value

Though some scattered critical issues are discussed in different literature, the critical issues of the Bangladeshi construction industry were not investigated extensively. Therefore, this study finds out the potential critical issues of the construction industry of Bangladesh to accumulate such harmful construction issues in a single platform so that the construction industry can have an overview of them with the help of innovative technologies.

Details

International Journal of Building Pathology and Adaptation, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 2398-4708

Keywords

Article
Publication date: 23 August 2022

Mohammad Nafe Assafi, Md. Mehrab Hossain, Nicholas Chileshe and Shuvo Dip Datta

As a developing nation, Bangladesh still has scarce technological applications in the construction sector, which results in construction delays. This paper aims to propose a…

Abstract

Purpose

As a developing nation, Bangladesh still has scarce technological applications in the construction sector, which results in construction delays. This paper aims to propose a framework that will diminish manual labor, reduce human error and apply four-dimensional (4D) building information modeling (BIM)-based solutions to mitigate and prevent construction project delays.

Design/methodology/approach

First, a systematic literature review was conducted on analyzing the construction delay scenario in the context of Bangladesh and other countries. Next, a 4D BIM-based framework was developed using Autodesk Navisworks Manage. Finally, it was used to run on-site simulations on an ongoing construction project which faced delays because of design errors and inefficient planning.

Findings

Affirmative results were found from applying these methods through real-time project simulation. The current status of the project and the status after using BIM technology were compared. It was observed that during both the preconstruction and execution phases, the application of 4D BIM could reduce the delay posed by design error and inefficient planning.

Practical implications

The project manager and the design engineers can use these frameworks to review their projects. For the design engineers, the preconstruction phase portion of the framework will help identify the probable errors in the design. For the project managers, keeping track of time using the execution phase portion of the framework will be resourceful.

Originality/value

To the best of the authors’ knowledge, this study is the first to assess the significant delay factors endemic in Bangladesh and develop a BIM-based technological solution. This study is solely dedicated to reforming the construction techniques in Bangladesh through the application of 4D BIM technology.

Details

Construction Innovation , vol. 23 no. 5
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 12 April 2022

Mohammad Nafe Assafi, Md. Ikramul Hoque and Md. Mehrab Hossain

Construction delay always causes massive damage to the advancing construction industries, which is no different in the case of Bangladeshi construction industries. This paper aims…

Abstract

Purpose

Construction delay always causes massive damage to the advancing construction industries, which is no different in the case of Bangladeshi construction industries. This paper aims to investigate the major delay factors causing construction delays in public-funded, mixed and private-funded construction projects of Bangladesh. Also, it offers preventive suggestions from expert stakeholders to reduce the recurrence of delays.

Design/methodology/approach

At first, an extensive literature review was conducted to identify the thirty-seven major delay factors categorized under seven groups. A questionnaire was then developed for survey at ongoing construction projects at a different division of Bangladesh. Next, data from 110 respondents were collected, and the delay factors were ranked based on the Relative Importance Index (RII); lastly, probable solutions were suggested for top-ranked delay factors based on opinions from expert stakeholders in the construction sector of Bangladesh.

Findings

The overall RII ranking of the 37 delay factors showed “Construction mistakes and defective work,” “Contract modifications by the client” and “Adverse weather condition” as the top three factors causing the delay. For public-funded projects, “Construction mistakes and defective work” and “Slow decision making by a consultant” are the top delay factors. For mixed projects, “Slow decision making of the client” and “Construction mistakes and defective work ranked top, and for private-funded projects, “Financial problems and payment delay of the client” and “Adverse weather condition” ranked top. These nuances of ranking in individual project types ascertain that the causes of delay vary in terms of project features.

Practical implications

The outcome of this project will help identify the significant delay factors based on their severity of effectiveness associated with public-funded, mixed and private-funded projects in Bangladesh. The suggestions regarding preventing these delay factors obtained through the opinions of expert stakeholders can help reduce the effect of these delays in the context of Bangladesh and in countries where the similarity in construction environment prevails.

Originality/value

Previously, studies on construction delays in Bangladesh focused mainly on identifying the delays using qualitative analysis techniques. This study is based on a unique methodology of integrating quantitative research on delay factor identification and qualitative research on preventive measures following the opinions gathered from expert stakeholders in the construction sector.

Details

International Journal of Building Pathology and Adaptation, vol. 42 no. 4
Type: Research Article
ISSN: 2398-4708

Keywords