1 – 1 of 1Ahmed Attar, Mohamed Amine Boudjakdji, Nadia Bhuiyan, Khaled Grine, Said Kenai and Ali Aoubed
The purpose of this paper is to show how the time frame for the execution of a construction project in Algeria is rarely respected because of organizational problems and…
Abstract
Purpose
The purpose of this paper is to show how the time frame for the execution of a construction project in Algeria is rarely respected because of organizational problems and uncertainties encountered while the execution is underway.
Design/methodology/approach
A case study on the construction of a metro station is used as a pilot project to show the effectiveness of replacing traditional construction processes by more innovative procedures. Concurrent engineering (CE) is applied to optimize the execution time of the underground structure. A numerical simulation is integrated into the construction process in order to update design parameters with real site conditions observed during the construction process.
Findings
The results show that the implementation of CE is efficient in reducing the completion time, with an 18 per cent reduction observed in this case study. A cost reduction of 20 per cent on the steel frame support and a total cost reduction of 3 per cent were obtained.
Research limitations/implications
The study demonstrates that the application of CE methods can be quite valuable in large, complex construction projects. Vulgarizing it as “the solution” to adjust time frame delay, control quality and cost, might be an issue for local construction enterprises in Algeria.
Originality/value
Using the concept of CE by overlapping different activities involved in a construction project and making use of simulation tools in the process at different stages of the execution have resulted in modifying the excavation method and hence reducing the completion times.