Publication date: 21 May 2018

Parvaneh Shahsavand, Akbar Marefat and Majid Parchamijalal

The purpose of this paper is to reveal the main causes of delays in the projects are from the client (relative importance index (RII)=0.716), labor and equipment (RII=0.701) and…

46824

Abstract

Purpose

The purpose of this paper is to reveal the main causes of delays in the projects are from the client (relative importance index (RII)=0.716), labor and equipment (RII=0.701) and contractor (RII=0.698). Hence determining the contractual responsibility of delay is the most likely source of dispute in construction projects and many techniques have been used in the courts to demonstrate the criticalities of a delay event on the project schedule. Therefore, authors try to investigate all process-based techniques of delay claims and evaluated and conformed them with principles by Society of Construction Law (SCL) protocol and Association for the Advancement of Cost Engineering International (AACEI) in order to choose the best techniques based on the specific circumstances of each project.

Design/methodology/approach

This section is divided into two distinct parts: refers to the methods used to assess the perceptions of clients, consultants, and contractors on the relative importance of causes of delay in construction industry; and refers to advantages and disadvantages of various techniques used to analyze delays and their conform with SCL protocol. A questionnaire was developed to assess the perceptions of clients, consultants, and contractors on the relative importance of causes of delay in Iranian construction industry. The respondents were asked to indicate their response category on 78 well-recognized construction delay factors identified by authors.

Findings

In total, 78 causes of delay were identified through research. The identified causes are combined into seven groups. The field survey included 58 contractors, 55 consultants, and 62 client. Data collected were analyzed by RII and Statistical Package for Social Sciences (SPSS). The authors identified main causes of delay and ten most important causes, according to Table AII, from the perspective of three major groups of participants (clients, consultants and contractors). The ranking of categories of causes of delay, according to Table I, were: client-related causes (RII=0.716); labor and equipment category causes (RII=0.701); contractor-related causes (RII=0.698); material-related causes (RII=0.690); design-related causes (RII=0.666); external causes (RII=0.662); and consultant-related causes (RII=0.662). But according to the discussions and given that determining the contractual responsibility of delay is the most likely source of dispute in construction industry and many techniques have been used in the courts to demonstrate the criticalities of a delay event on the project schedule.

Originality/value

All process-based techniques of delay analysis have been present in this paper and categorized in 11 groups. In order to understand the advantages and disadvantages of them by clients, contractor and consultant, a thorough review conducted to reveal the nature of techniques. In the next step, given that selecting the most appropriate technique based on constraints and specific conditions of each project is one of the most important steps to carry out a successful delay analysis. The authors conformed, all process-based techniques of delay analysis, by SCL protocol and AACEI principles. Finally, the result of this match was brought in order to choose the best technique based on the specific circumstances of each project.

Details

Engineering, Construction and Architectural Management, vol. 25 no. 4
Type: Research Article
ISSN: 0969-9988

Keywords

Access Restricted. View access options
Article
Publication date: 22 December 2021

Majid Parchamijalal, Saeed Moradi and Mohsen Zabihi Shirazi

Claim formation is a fact and a regular occurrence in construction industry projects and often leads to a waste of money and time for organizations. Organizations can, however…

734

Abstract

Purpose

Claim formation is a fact and a regular occurrence in construction industry projects and often leads to a waste of money and time for organizations. Organizations can, however, reduce and control claims by promoting an integrated claim management system and improving productivity in the results of the claims. Establishing a claim management office is one of the ways to help organizations achieve this.

Design/methodology/approach

Based on library research, expert opinion and analysis of organizations' contracts as case studies and identifying the root causes of the claim, this paper proposes a claim management office maturity model and determines its levels.

Findings

This paper proposes a claim management office maturity model and also determines its levels. The general structure of this model is based on three parameters: “characteristics of each level,” “requirements of each level” and “transition period of each level” in five levels, where the first level is the most basic level and level five is the highest level of the implementation of a claim management office in the organization.

Originality/value

It can be clearly emphasized that this research is one of the first research studies that has dealt with the issue of claim management office in the construction industry and has proposed the model of maturity and development of claim management office in the organization. The use of numerous and experienced experts in achieving the results and case organizations to develop this research has increased the value and credibility of this research. This study also helps to improve the level of claim management in construction industry organizations so that these organizations can implement each level of claim management maturity model in the organization according to their competence and need for claim management. And by implementing it correctly, solve or reduce the problems of claim management in the organization and their projects.

Details

Engineering, Construction and Architectural Management, vol. 30 no. 1
Type: Research Article
ISSN: 0969-9988

Keywords

Access Restricted. View access options
Article
Publication date: 30 December 2021

Shahab Shoar, Tak Wing Yiu, Shamsi Payan and Majid Parchamijalal

Although several studies have been conducted on the causes of cost overrun, they have mainly assumed that the causes of cost overrun are independent of each other, and few of them…

1386

Abstract

Purpose

Although several studies have been conducted on the causes of cost overrun, they have mainly assumed that the causes of cost overrun are independent of each other, and few of them scrutinized the complex interrelationships between the causes. To fill the gap, this study aims to investigate the mutual interactions between the causes of cost overrun using interpretive structural modeling (ISM) and proposing strategies to tackle the causes considering their interactions.

Design/methodology/approach

Critical causes of cost overrun were identified through a comprehensive literature review. In total, 22 key causes are then refined based on the opinions of relevant experts involved in the Iranian building and construction sector. Using the nominal group technique, the causes' interactions were examined and represented via the ISM diagram. The causes were also classified using “matrix cross-reference multiplication applied to a classification (MICMAC)” technique.

Findings

The results showed that price fluctuation, claims, execution delay, delay in payment and change order positioned at the highest level of the obtained model can directly result in cost overrun, and corruption and poor contract management located at the base of the model are two major root causes of cost overruns. It was also concluded that more attention should be paid to the precontract phase of the project to address and prevent corruption and managerial issues deeply rooted in this stage.

Originality/value

The findings of this study provide a clear understanding of how different causes of cost overrun are related to each other and can ultimately assist project managers of different parties in choosing strategies to mitigate cost overrun in building construction projects.

Details

Engineering, Construction and Architectural Management, vol. 30 no. 2
Type: Research Article
ISSN: 0969-9988

Keywords

Access Restricted. View access options
Article
Publication date: 5 June 2020

Majid Parchami Jalal, Tayebe Yavari Roushan, Esmatullah Noorzai and Maryam Alizadeh

This study aims at introducing a claim management model based on building information modeling (BIM) for claims that can be visualized in BIM models.

887

Abstract

Purpose

This study aims at introducing a claim management model based on building information modeling (BIM) for claims that can be visualized in BIM models.

Design/methodology/approach

Based on the results of a questionnaire survey, 10 claims were identified as claims that can be visualized in BIM models (named hard claims in this study). Then, a BIM-based claim management model was developed and used in a case study.

Findings

A BIM-based claim management model is represented. The claim management process through this model consists of four steps: (1) extracting project information, identifying conditions prone to claim and storing them into a relational database, (2) automatically connecting the database to building information model, (3) simulation of the claims in building information model and (4) final calculations and report.

Practical implications

The proposed model can provide benefits to parties involved in a claim, such as early identification of potential claims, large space for data storage, facilitated claim management processes, information consistency and improved collaboration.

Originality/value

There are a few studies on providing solutions to claim management based on BIM process. Hence, the original contribution of this paper is the attempt to set a link between BIM and claim management processes.

Access Restricted. View access options
Article
Publication date: 7 October 2019

Majid Parchami Jalal and Shahab Shoar

This paper aims to model different causal relations among factors interacting with labour productivity in order to recognize the most important factors influencing and influenced…

763

Abstract

Purpose

This paper aims to model different causal relations among factors interacting with labour productivity in order to recognize the most important factors influencing and influenced by it.

Design/methodology/approach

Top 60 factors affecting labour productivity were determined and grouped into 5 major groups by reviewing previous research and interviewing relevant experts. The interactions of factors were modelled using system dynamics (SD) approach. The resulting causal loop diagrams obtained from SD were then applied for identifying the most crucial factors influencing and influenced by labour productivity through the decision-making trial and evaluation laboratory (DEMATEL) method. The impact of factors on each other was finally determined based on the opinions of 63 experts selected from the Iranian construction industry.

Findings

The results indicated that factors such as fatigue, lack of labour motivation and lack of skill are the most influencing, and factors such as schedule delay and inflation in the cost of execution are the most influenced by labour productivity. In the end, a set of recommendations to improve construction labour productivity was also presented.

Originality/value

The main contribution of the study is proposing a novel method which is capable of providing insights into how causes and effects of construction labour productivity are interrelated. Furthermore, the proposed method makes this study distinct from previous research in the light of prioritizing factors and offering recommendations according to the interrelationships among factors.

Access Restricted. View access options
Article
Publication date: 17 July 2017

Majid Parchami Jalal and Shahab Shoar

The purpose of this paper is to develop a model for complex interconnected structure of various factors interacting with delay in order to identify the most important factors…

751

Abstract

Purpose

The purpose of this paper is to develop a model for complex interconnected structure of various factors interacting with delay in order to identify the most important factors influencing and influenced by delay based on their interrelations.

Design/methodology/approach

Reviewing literature and interviewing with local experts selected from the Iranian construction industry, top 58 delay factors were identified and categorized into six major groups. The interrelations among these factors were, then, modeled using the system dynamics (SD) approach. The resulting causal loop diagrams obtained from SD were used subsequently for identifying the most significant factors influencing and influenced by delay through the Decision Making Trial and Evaluation Laboratory (DEMATEL) method. The impact of factors on each other was finally determined based on the opinions of 63 experts selected from the Iranian community of consultants, contractors, and clients.

Findings

According to the analysis, eight out of the 58 factors were identified as the most influencing factors on delay, and nine factors were found to be the most influenced factors by delay in the field of delay analysis. The study also concluded that factors related to labors are the most important and influential factors. In addition, factors related to client were the most influencing factors and external-related factors were the least important ones. At the end, some recommendations to reduce variation of delay in the construction projects are presented as well.

Originality/value

Considering the interconnected structure of the factors, the paper identifies the most important factors interacting with time delay in construction projects.

Details

Engineering, Construction and Architectural Management, vol. 24 no. 4
Type: Research Article
ISSN: 0969-9988

Keywords

Access Restricted. View access options
Article
Publication date: 15 February 2021

Parisa Amirtash, Majid Parchami Jalal and Mostafa Babaeian Jelodar

International Engineering, Procurement and Construction (IEPC) projects deliver complex and critical infrastructure and construction projects. However, these projects face…

1353

Abstract

Purpose

International Engineering, Procurement and Construction (IEPC) projects deliver complex and critical infrastructure and construction projects. However, these projects face multiple challenges, especially in foreign construction markets, to the main contractors. The purpose of this article is to develop a tool for effective implementation of project management services for these international projects through upskilling and incorporate local expertise. Accordingly, the employment of a Native Project Management Consultant (NPMC) by the main contractor is proposed and investigated.

Design/methodology/approach

A three-stage research method was employed for triangulation of knowledge. Initially, a comprehensive literature review was carried out to examine the theoretical foundations of the study. The concepts were further explored through a survey and expert interviews. The study was performed in Iran as the host nation of multiple IEPC projects.

Findings

It was found that NPMC involvement has a significant contribution to the success of nearly all project management areas in IEPC projects. However, quality, schedule and budget management were the top-ranked areas. The study combines the results of previous studies with the interviews and questionnaire to create a tool designed to capture strategy actions and detailed activities designed to build capabilities in IEPC teams through the involvement of NPMCs.

Practical implications

A practical tool is developed which aims to enhance NPMC integration into IEPC projects. The tool is in-line with the project management concept of work-breakdown structure; which is understandable by project stakeholders.

Originality/value

The employment of NPMCs, and their potential role in IEPC projects has not been formally investigated and guidelines for such collaborations do not exist. The current study provides a platform for regulating such facilitators and enhancing project success.

Details

Built Environment Project and Asset Management, vol. 11 no. 2
Type: Research Article
ISSN: 2044-124X

Keywords

Access Restricted. View access options
Article
Publication date: 17 October 2018

Ting-Kwei Wang, David N. Ford, Heap-Yih Chong and Wei Zhang

Delays during construction are one of the common scenarios in the construction industry. The purpose of this paper is to identify the primary causes of delays in the construction…

1982

Abstract

Purpose

Delays during construction are one of the common scenarios in the construction industry. The purpose of this paper is to identify the primary causes of delays in the construction phase of building construction projects in China.

Design/methodology/approach

Questionnaire survey approach was adopted across the four typical cities in China, namely, Beijing, Shanghai, Chongqing and Shenzhen. In total, 115 sets of valid responded questionnaires were collected and analyzed.

Findings

The results show that the causes of variations, delays in progress payments, exceptionally low bids and subcontractors’ poor performance and communication issues were the most important causes of delays in China.

Originality/value

This research is the first questionnaire survey on the causes of delays in the construction phase of building construction projects in China. The comparative analysis shows two unique causes of delays in the Chinese construction industry, such as “difficulty in claiming indemnity” and “unreasonable upfront capital demanded by client.” It also reveals different ranked causes of delays as per distinguished political and economic situations in China. The research findings can be referred by construction projects in other countries that are funded or partnered with China.

Details

Engineering, Construction and Architectural Management, vol. 25 no. 11
Type: Research Article
ISSN: 0969-9988

Keywords

Access Restricted. View access options
Article
Publication date: 16 August 2024

Dickson Osei-Asibey, Joshua Ayarkwa, Benjamin Baah, Aba Essanowa Afful, Gloria Anokye and Prince Asher Nkrumah

Many investors have less interest in tendering for public-private partnership (PPP) construction projects as a result of the uncertain risks associated with the project delivery…

147

Abstract

Purpose

Many investors have less interest in tendering for public-private partnership (PPP) construction projects as a result of the uncertain risks associated with the project delivery. Moreover, PPP project stakeholders have inadequate information about the probable impacts of time-based delay imposed on PPP projects under the PPP arrangement. This study aims to identify and categorize construction stakeholders’ perceptions of the impact of time-based delays on PPP construction projects.

Design/methodology/approach

A purposive sampling technique was adopted where questionnaires were used as the primary instrument for gathering data from PPP experts. Cronbach’s alpha coefficient and Kendall’s concordance were used to measure the reliability of the scale and the respondent’s level of agreement, respectively. One sample t-test, mean score ranking and principal component analysis were used to analyse the identified time-based delay impacts.

Findings

The study revealed seven significant impacts of time-based delay on PPP construction project delivery as: “project schedule overrun”, “idling of project resources”, “project cost overrun”, “poor quality of completed works”, “delayed realization of project benefits”, “frequent arbitration/litigation in PPP projects” and “total abandonment of PPP projects”. The study further identified the top five significant impacts of time-based delay on PPP project stakeholders as: “reduction in motivation to attract investment”, “high interest on finance (loans)”, “contractor in financial crisis”, “loss of public confidence in government” and “reduction in parties’ reputation”.

Practical implications

The identified significant impacts of time-based delays will increase stakeholders’ awareness of the repercussions and effects that time-based delays may impose on PPP construction projects if not appropriately managed throughout the project implementation. This awareness will further guide stakeholders to implement targeted risk management strategies to minimize the negative consequences of delays on PPP project performance.

Originality/value

As a pioneering study that provides a better understanding of the impacts of time-based delays on PPP construction projects, this study enhances knowledge of PPP construction project implementation.

Details

Journal of Financial Management of Property and Construction , vol. 30 no. 1
Type: Research Article
ISSN: 1366-4387

Keywords

Access Restricted. View access options
Article
Publication date: 8 March 2024

Md. Mohaimenul Islam Sourav, Mohammed Russedul Islam, Sheikh Mohibur Rahman and Md. Istiak Jahan

In Bangladesh (BD), delays in infrastructure are common. Many previous studies have explored the causes of infrastructure delays. However, this study investigated the causes of…

114

Abstract

Purpose

In Bangladesh (BD), delays in infrastructure are common. Many previous studies have explored the causes of infrastructure delays. However, this study investigated the causes of delays by taking responses from the stakeholders who are responsible for planning, design, funding, approval and implementation. There are few studies that have related infrastructure project delays to heterogeneity in stakeholders’ perceptions.

Design/methodology/approach

A structural equation (SE) model is developed with 350 normally distributed data points to understand the heterogeneity in stakeholders’ perceptions regarding delays in infrastructure projects in BD. Additionally, the relative importance index (RII) approach is used to assess the responses, validating the SE model.

Findings

The study finds that among the three latent variables, “Project itself related delay” has more influence on delays in infrastructure projects. Among the observed variables under the “project itself related delay” latent variable, “DPP approval process” has the most significance. From the heterogeneity analysis, the study found differences in responses among the stakeholders from “the Engineering Department,” “the Planning Office” and “the Construction Firm/Industry.” An important class of stakeholders believes that their stage is not being delayed and that other stages require attention.

Research limitations/implications

The data sample is 350. More data can improve the accuracy of the findings. Most of the respondents are civil engineers (74%) and represent the owner of the project. Sample data from more stakeholders’ will enhance the accuracy of the result.

Practical implications

This study addresses the requirements of Bangladeshi project stakeholders and how their interactions cause delays in projects. Furthermore, the opinions of other stakeholders are taken into consideration when determining the specific factors of individual stakeholders that are causing delays. Practically, the distance between stakeholders should be reduced. A project manager can play a role in this regard. Initiatives should be taken on how to complete the project quickly by eliminating the requirements discussed among the stakeholders and bureaucratic complications. Instead of placing blame on one another, stakeholders should take the initiative to figure out how to work together to finish the project on schedule. The Planning Commission’s approval of the Development Project Proposal (DPP) and Revised Development Project Proposal (RDPP) should be obtained as soon as possible by owner stakeholders. In order to avoid frequently changing the DPP, owners should also exercise greater caution when choosing contractors. Contractor stakeholders should use efficient and proper manpower and equipment so that unexpected delays are not created during the execution of work. Since the role of the contractor stakeholder is the most important among the three types of stakeholders, the contractor should raise awareness and urge the owners to get the RDPP approved quickly.

Originality/value

The findings from the study can help mitigate delays in infrastructure projects in BD, taking into account the perceptions of various stakeholders.