Search results

1 – 4 of 4
Per page
102050
Citations:
Loading...
Access Restricted. View access options
Article
Publication date: 6 June 2020

Atle Engebø, Ole Jonny Klakegg, Jardar Lohne and Ola Lædre

To achieve the shift towards sustainable construction the industry must change the project delivery methods used. Therefore, this paper reports on a high-performance building…

1264

Abstract

Purpose

To achieve the shift towards sustainable construction the industry must change the project delivery methods used. Therefore, this paper reports on a high-performance building project that implemented a collaborative project delivery method through the examination of the following research questions: RQ1: What were the most important contractual, cultural and organisational elements studied in the collaborative project delivery method? RQ2: What were the effects of the studied elements?

Design/methodology/approach

A longitudinal case study approach was adopted. As for means of data collection, a document review, semi-structured interviews, and observations was conducted. A total of 20 observations (App. 80 h, 175 pages of notes) and 12 interviews (App. 20 h, 100 pages of notes) with project participants was conducted.

Findings

The analysis indicates that if attention is paid to task, team and individual needs through contractual, cultural and organisational elements, this will affect the development of an integrated team.

Research limitations/implications

We demonstrate that the effects of the elements are shown through their achievement in creating and sustaining an integrated team of inter-organisational participants working in a collaborative environment.

Practical implications

It provides a better understanding of how a collaborative project delivery method for the design phase emphasises team integration. We demonstrate that while the principal sets the contractual boundaries by deciding the contractual elements, the agent should be intentional in the selection and use of organizational and cultural elements.

Originality/value

The paper suggests that it is not enough to just have contractual elements implemented. Consequently, this insight suggests that managers should be attentive to the untapped potential that lies within organisational and cultural elements.

Details

International Journal of Managing Projects in Business, vol. 13 no. 6
Type: Research Article
ISSN: 1753-8378

Keywords

Access Restricted. View access options
Article
Publication date: 29 May 2024

Gro Holst Volden, Morten Welde, Atle Engebø and Bjørn Sørskot Andersen

In the project initiation phase, an appraisal is needed to clarify the strategic problem and alternative solutions. Full-scale construction projects and simple solutions …

187

Abstract

Purpose

In the project initiation phase, an appraisal is needed to clarify the strategic problem and alternative solutions. Full-scale construction projects and simple solutions (do-minimum alternatives) should be assessed. The do-nothing alternative is the baseline for the appraisal and an option in itself. The paper explores the role of do-nothing and do-minimum alternatives in public project appraisal, which may significantly impact the attractiveness of a construction project.

Design/methodology/approach

The paper presents an empirical study from Norway, which requires external quality assurance (QA) of early project appraisals. The data include an extensive document review of 112 projects and interviews with 41 experts involved in the appraisal processes.

Findings

Of 112 appraisals, 110 recommended a major construction project, including cases where the benefits and value were low or uncertain. The do-nothing alternative was generally included as a reference but not treated as a viable option. Do-minimum alternatives were often not explored. By contrast, the external QA reports recommended do-nothing or do-minimum in 28 cases. Interestingly, although political decision-makers rarely reject projects, they may put them on hold indefinitely, implying that the actual outcome in many cases is still do-nothing.

Originality/value

The paper addresses a topic that has been understudied in the literature. The findings contribute to the broader literature on project initiation processes, project appraisal and how to reduce the risk of bias and manipulation in appraisals.

Details

International Journal of Managing Projects in Business, vol. 17 no. 3
Type: Research Article
ISSN: 1753-8378

Keywords

Available. Open Access. Open Access
Book part
Publication date: 1 May 2019

Per Fridtjof Larssen, Atle Engebø, Ola Lædre and Ole Jonny Klakegg

This paper aims to examine how a partnering contract facilitates project values and the culture in a construction project and the consequences of said facilitation. Hence, it…

Abstract

Purpose

This paper aims to examine how a partnering contract facilitates project values and the culture in a construction project and the consequences of said facilitation. Hence, it answers the following research questions: 1) How does the contractual framework in Bispevika facilitate relational culture? 2) What effects of this facilitation can be identified in the early phase of development?

Design/Methodology/Approach

An explorative approach is taken into a single case. A literature study into the topics of relational contracting and culture provides a backdrop for the study. The empirical work consists of a study of the construction contracts and six in-depth interviews with actors from the supply-chain.

Findings

Contractual elements affect the project organizations’ motivation. On the basis of existing literature, five contractual elements are identified explicitly in the contracts: “shared goals”, “incentives and bonus”, “open book”, “colocation”, and “design-build”.

Research Limitations/Implications

The data collection is restricted to a single point in time in a single project. Further research is necessary both at a later stage in the same case and in similar projects.

Practical Implications

The paper identifies the effects that proper use of contractual elements has on the relational culture in a construction project and is, therefore, important for subsequent research within the area.

Originality/Value

In addition to identifying the existing contractual elements, the interviews also revealed two additional practices that might be useful for subsequent research: “involvement of executive management” and “subsequent contracts dependent on previous project performance”.

Details

10th Nordic Conference on Construction Economics and Organization
Type: Book
ISBN: 978-1-83867-051-1

Keywords

Available. Open Access. Open Access
Book part
Publication date: 1 May 2019

Abstract

Details

10th Nordic Conference on Construction Economics and Organization
Type: Book
ISBN: 978-1-83867-051-1

1 – 4 of 4
Per page
102050