Saleh Alsulamy

The purpose of this research is to identify the constraints and restrictions and their impact on the construction projects in Saudi Arabia from three key participants'…

3924

Abstract

Purpose

The purpose of this research is to identify the constraints and restrictions and their impact on the construction projects in Saudi Arabia from three key participants' perspectives for the planning stage.

Design/methodology/approach

Using a descriptive-analytical approach, this research described and analyzed the frequency and severity of failure factors in construction projects in the planning stage using a five-Likert scale questionnaire in Saudi Arabia construction between 2019 and 2020. A total of 100 experts from contractors, consultants and owners were included in the study.

Findings

The findings have shown that time dispute was the major factor affecting the projects to be failed. Similarly, cost overrun and total abandonment have an impact on project failures. The findings have indicated that government officials were involved in delaying the projects while contractors also failed in the project deliveries.

Research limitations/implications

Further research is needed to investigate the relationship between failure characteristics and project success measures in the same stage, in addition to, factors of failure for construction projects' life-cycle stages.

Originality/value

The findings have indicated that government officials were involved in delaying the projects while contractors also failed in the project deliveries.