This study aims to improve a construction company's overall project delivery by utilising lean six sigma (LSS) methods combined with building information modelling (BIM) to…
Abstract
Purpose
This study aims to improve a construction company's overall project delivery by utilising lean six sigma (LSS) methods combined with building information modelling (BIM) to design, modularise and manufacture various building elements in a controlled factory environment off-site.
Design/methodology/approach
A case study in a construction company utilised lean six sigma (LSS) methodology and BIM to identify non-value add waste in the construction process and improve sustainability.
Findings
An Irish-based construction company manufacturing modular pipe racks for the pharmaceutical industry utilised LSS to optimise and standardise their off-site manufacturing (OSM) partners process and leverage BIM to design skids which could be manufactured offsite and transported easily with minimal on-site installation and rework required. Productivity was improved, waste was reduced, less energy was consumed, defects were reduced and the project schedule for completion was reduced.
Research limitations/implications
The case study was carried out on one construction company and one construction product type. Further case studies would ensure more generalisability. However, the implementation was tested on a modular construction company, and the methods used indicate that the generic framework could be applied and customized to any offsite company.
Originality/value
This is one of the few studies on implementing offsite manufacturing (OSM) utilising LSS and BIM in an Irish construction company. The detailed quantitative benefits and cost savings calculations presented as well as the use of the LSM methods and BIM in designing an OSM process can be leveraged by other construction organisations to understand the benefits of OSM. This study can help demonstrate how LSS and BIM can aid the construction industry to be more environmentally friendly.
Rita Lavikka, Krishna Chauhan, Antti Peltokorpi and Olli Seppänen
Systemic innovations emerge and create value in an inter-organisational context. However, innovation studies rarely investigate the role of value creation and value capture among…
Abstract
Purpose
Systemic innovations emerge and create value in an inter-organisational context. However, innovation studies rarely investigate the role of value creation and value capture among multiple organisations in successful innovation implementation. This paper aims to understand the role of value creation and value capture in the implementation of systemic innovations in construction which is by nature, an inter-organisational context.
Design/methodology/approach
The empirical research focused on the barriers, enablers and opportunities for value creation and value capture of the Finnish construction project parties when trying to implement mechanical, electrical and plumbing (MEP) prefabrication, which is a systemic innovation. Data were collected through interviews, observations and action workshops.
Findings
The empirical study identified interaction patterns on how social, political, technical and economic barriers lead to uneven value capturing, lack of value-based procurement and unclear value creation between MEP design and installation. They hinder the implementation of MEP prefabrication. The results point to enablers leading to fairly shared value to all parties, procurement of value and collaborative value creation, thus increasing the usage of MEP prefabrication, a systemic innovation.
Originality/value
The study adds new knowledge by demonstrating that the identification of barriers and their interaction with enablers and opportunities for value creation and capture lay a baseline for suggestions on how to implement a systemic innovation. This study stresses the importance of enabling value creation and capture for all construction project parties when implementing a systemic innovation.
Details
Keywords
Tan Tan, Grant Mills, Xiaolin Ma and Eleni Papadonikolaki
Off-Site Construction (OSC) has received much government and public attention during and after COVID. Building Information Modelling (BIM) is an initiative discussed widely to…
Abstract
Purpose
Off-Site Construction (OSC) has received much government and public attention during and after COVID. Building Information Modelling (BIM) is an initiative discussed widely to promote OSC implementation. Although many policy promotions have been published, there are many challenges to implementing BIM and OSC in real life and questions of whether they really offer value to healthcare design professionals. This research aims to investigate BIM and OSC to understand their commonalities and differences of challenges by collecting empirical evidence from China’s healthcare construction.
Design/methodology/approach
This exploratory research adopted a mixed method with a questionnaire survey and interviews. A total of 261 questionnaires were received (with 183 valid), followed by 31 semi-structured interviews.
Findings
This research reveals that although both OSC and BIM face similar adoption challenges and suspicious attitudes in real-life projects, their challenges’ connotations and reasons are different. OSC faces scepticism for its customisation costs and technical constraints, while BIM is seen as limited in utility and complex to integrate. Highlighting these as socio-technical challenges, the research advocates for an integrated framework to effectively implement OSC and BIM, addressing both technical and collaborative needs in healthcare construction.
Originality/value
This research examines OSC and BIM within the context of healthcare construction, a focus that is relatively underexplored. The research provides a juxtaposition of the perceived and practical challenges of adopting these technologies, revealing a gap between the industry’s expectations and the current capabilities of OSC and BIM, thereby contributing to the development of modern methods of design in healthcare.
Details
Keywords
Lars Stehn and Alexander Jimenez
The purpose of this paper is to understand if and how industrialized house building (IHB) could support productivity developments for housebuilding on project and industry levels…
Abstract
Purpose
The purpose of this paper is to understand if and how industrialized house building (IHB) could support productivity developments for housebuilding on project and industry levels. The take is that fragmentation of construction is one explanation for the lack of productivity growth, and that IHB could be an integrating method of overcoming horizontal and vertical fragmentation.
Design/methodology/approach
Singe-factor productivity measures are calculated based on data reported by IHB companies and compared to official produced and published research data. The survey covers the years 2013–2020 for IHB companies building multi-storey houses in timber. Generalization is sought through descriptive statistics by contrasting the data samples to the used means to control vertical and horizontal fragmentation formulated as three theoretical propositions.
Findings
According to the results, IHB in timber is on average more productive than conventional housebuilding at the company level, project level, in absolute and in growth terms over the eight-year period. On the company level, the labour productivity was on average 10% higher for IHB compared to general construction and positioned between general construction and general manufacturing. On the project level, IHB displayed an average cost productivity growth of 19% for an employed prefabrication degree of about 45%.
Originality/value
Empirical evidence is presented quantifying so far perceived advantages of IHB. By providing analysis of actual cost and project data derived from IHB companies, the article quantifies previous research that IHB is not only about prefabrication. The observed positive productivity growth in relation to the employed prefabrication degree indicates that off-site production is not a sufficient mean for reaching high productivity and productivity growth. Instead, the capabilities to integrate the operative logic of conventional housebuilding together with logic of IHB platform development and use is a probable explanation of the observed positive productivity growth.
Details
Keywords
The future construction site will be pervasive, context aware and embedded with intelligence. The purpose of this paper is to explore and define the concept of the digital skin of…
Abstract
Purpose
The future construction site will be pervasive, context aware and embedded with intelligence. The purpose of this paper is to explore and define the concept of the digital skin of the future smart construction site.
Design/methodology/approach
The paper provides a systematic and hierarchical classification of 114 articles from both industry and academia on the digital skin concept and evaluates them. The hierarchical classification is based on application areas relevant to construction, such as augmented reality, building information model-based visualisation, labour tracking, supply chain tracking, safety management, mobile equipment tracking and schedule and progress monitoring. Evaluations of the research papers were conducted based on three pillars: validation of technological feasibility, onsite application and user acceptance testing.
Findings
Technologies learned about in the literature review enabled the envisaging of the pervasive construction site of the future. The paper presents scenarios for the future context-aware construction site, including the construction worker, construction procurement management and future real-time safety management systems.
Originality/value
Based on the gaps identified by the review in the body of knowledge and on a broader analysis of technology diffusion, the paper highlights the research challenges to be overcome in the advent of digital skin. The paper recommends that researchers follow a coherent process for smart technology design, development and implementation in order to achieve this vision for the construction industry.
Details
Keywords
Petra Bosch-Sijtsema, Christina Claeson-Jonsson, Mikael Johansson and Mattias Roupe
This paper aims to focus on 11 digital technologies (i.e. building information modeling, artificial intelligence and machine learning, 3D scanning, sensors, robots/automation…
Abstract
Purpose
This paper aims to focus on 11 digital technologies (i.e. building information modeling, artificial intelligence and machine learning, 3D scanning, sensors, robots/automation, digital twin, virtual reality, 3D printing, drones, cloud computing and self-driving vehicles) that are portrayed in future trend reports and hype curves. The study concentrates on the current usage and knowledge of digital technologies in the Swedish architecture, engineering and construction (AEC) industry to gain an insight in the possible expectations and future trajectory of these digital technologies.
Design/methodology/approach
The study applies an abductive approach which is based on three different types of methods. These methods are a literature and document study which focused on 11 digital technologies, two workshops with industry (13 participants) and an online survey (N = 84).
Findings
The paper contributes to a current state analysis of the Swedish AEC industry concerning digital technologies and discusses the trajectory of these technologies for the AEC industry. The paper identifies hype factors, in which the knowledge of a digital technology is related to its usage. From the hype factors, four zones that show different stages of digital technology usage and maturity in the industry are induced.
Originality/value
The contribution of the paper is twofold. The paper shows insight into opportunities, the current barriers, use and knowledge of digital technologies for the different actors in the AEC industry. Furthermore, the study shows that the AEC industry is behind the traditional Gartner hype curves and contributes with defining four zones for digital technologies for the Swedish AEC industry: confusion, excitement, experimentation and integration.
Details
Keywords
Brandsford Kwame Gidigah, Kofi Agyekum and Bernard Kofi Baiden
There is proliferation of regulatory frameworks and guidelines globally to implement social considerations in the procurement of construction projects. However, there are scanty…
Abstract
Purpose
There is proliferation of regulatory frameworks and guidelines globally to implement social considerations in the procurement of construction projects. However, there are scanty empirical studies that have researched into the implementation of social consideration in the procurement of construction projects in Africa, particularly Ghana. Therefore, this study aims to examine the challenges that hinder the implementation of social value in the procurement of construction works in Ghana.
Design/methodology/approach
The study used an explanatory sequential mixed-methods design with an initial quantitative instrument phase, followed by a qualitative data collection phase. A critical comparative review of the related literature resulted in the identification of 29 challenges. A total of 100 questionnaire responses from professionals in the construction industry in Ghana based on the challenges on the implementation of social value were retrieved. The data obtained were coded with SPSS version 22, analysed descriptively (mean scores and standard deviation) and via inferential analysis (exploratory factor analysis). These data were then validated through semi-structured interviews with 10 professionals. The data obtained from the semi-structured validation interviews were analysed through the side-by-side comparison of the qualitative data with the quantitative data.
Findings
The results revealed that the critical challenges to the implementation of social value in the procurement of construction works can be clustered into three major components, i.e. weak processes and bureaucracy, the incongruence of social value with the traditional procurement process, and the misaligned social targets and erosion of public procurement principles. The interviewees agreed to and confirmed the criticality of these factors as challenges to the implementation of social value in the procurement of construction works.
Research limitations/implications
A substantial number of studies have identified numerous challenges to the implementation of social value. This study presents a major cluster of challenges to the implementation of social value. Social value through construction procurement is a strategic tool globally and Ghana can leverage on its multiplier effects for social development.
Originality/value
The study extends the global discourse on social value in construction management literature by providing empirical evidence on the cluster of challenges that have the potential to hinder the implementation of social value in the procurement of construction works.