Scaling up smart city infrastructure projects will require a large financial investment. Using public–private partnerships is one of the most effective ways to address budget…
Abstract
Purpose
Scaling up smart city infrastructure projects will require a large financial investment. Using public–private partnerships is one of the most effective ways to address budget constraints. Numerous factors have varying degrees of influence on the performance of Public private partnerships (PPP) projects; certain PPP factors are more crucial to the success of a smart city infrastructure project than others, and their influence can be greatly increased when they are fulfilled collectively. This study aims to find out what factors are unique to smart city PPP initiatives, as well as how these factors work together, so that successful smart city infrastructure PPP projects can be scaled up.
Design/methodology/approach
The methodology included three sequential stages: identifying the critical success factors (CSF) of PPP for smart cities based on an extensive literature review, collecting data from a sample of 90 PPP practitioners using a Likert scale questionnaire and estimating interrelationships among the CSF and their emergent clusters using structural equation modelling.
Findings
The best fit model developed in this study demonstrated the significance of each factor and their interrelationships within their categories in enhancing the performance of PPPs in smart city infrastructure projects. Five categories of critical success factors for PPPs in smart city infrastructure projects have been established: partnership and collaboration; financial sustainability; contractual duties and outsourcing; smart integration; and contract governance.
Practical implications
The proposed model represented the causal interrelationships among relevant critical success factors derived from literature, which may help in directing the organization’s attention and resources to more critical areas, leading to the effective fulfilment of the smart city infrastructure project’s objectives. In addition to the theoretical and methodological contributions, this study produced a usable and readily adaptable list and clusters of critical success factors for research in the area of the implementation of PPP in smart city infrastructure projects.
Originality/value
To the best of the authors’ knowledge, this is the first study to identify PPP critical success factors and their themed clusters for smart city infrastructure projects.
Details
Keywords
Dickson Osei-Asibey, Joshua Ayarkwa, Benjamin Baah, Aba Essanowa Afful, Gloria Anokye and Prince Asher Nkrumah
Many investors have less interest in tendering for public-private partnership (PPP) construction projects as a result of the uncertain risks associated with the project delivery…
Abstract
Purpose
Many investors have less interest in tendering for public-private partnership (PPP) construction projects as a result of the uncertain risks associated with the project delivery. Moreover, PPP project stakeholders have inadequate information about the probable impacts of time-based delay imposed on PPP projects under the PPP arrangement. This study aims to identify and categorize construction stakeholders’ perceptions of the impact of time-based delays on PPP construction projects.
Design/methodology/approach
A purposive sampling technique was adopted where questionnaires were used as the primary instrument for gathering data from PPP experts. Cronbach’s alpha coefficient and Kendall’s concordance were used to measure the reliability of the scale and the respondent’s level of agreement, respectively. One sample t-test, mean score ranking and principal component analysis were used to analyse the identified time-based delay impacts.
Findings
The study revealed seven significant impacts of time-based delay on PPP construction project delivery as: “project schedule overrun”, “idling of project resources”, “project cost overrun”, “poor quality of completed works”, “delayed realization of project benefits”, “frequent arbitration/litigation in PPP projects” and “total abandonment of PPP projects”. The study further identified the top five significant impacts of time-based delay on PPP project stakeholders as: “reduction in motivation to attract investment”, “high interest on finance (loans)”, “contractor in financial crisis”, “loss of public confidence in government” and “reduction in parties’ reputation”.
Practical implications
The identified significant impacts of time-based delays will increase stakeholders’ awareness of the repercussions and effects that time-based delays may impose on PPP construction projects if not appropriately managed throughout the project implementation. This awareness will further guide stakeholders to implement targeted risk management strategies to minimize the negative consequences of delays on PPP project performance.
Originality/value
As a pioneering study that provides a better understanding of the impacts of time-based delays on PPP construction projects, this study enhances knowledge of PPP construction project implementation.
Details
Keywords
Divya Divya, Savita Savita and Sandeepa Kaur
This paper aims to provide a conceptual framework containing SERVQUAL original dimensions and add two additional dimensions: patient satisfaction and loyalty in the hospital SQ…
Abstract
Purpose
This paper aims to provide a conceptual framework containing SERVQUAL original dimensions and add two additional dimensions: patient satisfaction and loyalty in the hospital SQ model that demonstrates the relationship between hospital service quality, patient satisfaction and loyalty from patients’ perspective.
Design/methodology/approach
This research conducted a thorough literature review using specific keywords and electronic databases, adhering to Preferred Reporting Items for Systematic Reviews and Meta-Analyses (PRISMA) guidelines. Through analysis, the key dimensions of service quality in Indian hospitals were identified, with the addition of patient satisfaction and loyalty as variables. Of 1,000 initially downloaded papers, 497 were included.
Findings
While many researchers rely on the SERVQUAL model, some introduce new or modified dimensions, often renaming existing ones. This study identifies the RATER factors as the main dimensions patients use to evaluate hospital services. This study finds a positive relationship between service quality, patient satisfaction and loyalty.
Practical implications
An understanding of how health-care service quality dimensions, directly and indirectly, affect patient satisfaction and loyalty is important for hospital marketing managers. This study helps them take action to improve patient satisfaction, which encourages patients to be loyal.
Originality/value
This research provides a comprehensive framework for measuring health-care service quality, combining SERVQUAL dimensions and new variables. This study offers useful insights for academics and health-care professionals, promoting more accurate measurement and enhancement of service quality. The use of PRISMA in this context is also innovative, as it is less common in administrative health-care research.