Publication date: 10 December 2024

Jiaojiao Xu and Sijun Bai

The critical chain project buffer monitor process addresses uncertainty and variability in project duration. However, classical buffer monitor methods only consider buffer…

7

Abstract

Purpose

The critical chain project buffer monitor process addresses uncertainty and variability in project duration. However, classical buffer monitor methods only consider buffer consumption, while the dynamic allocation of buffer zones and the buffer consumption trend of activities are ignored. This paper presents the innovative framework for dynamic monitoring of project buffer which covers the dynamic buffer allocation, predictive analytics of buffer utilization and a new monitoring technique based on control chart graph.

Design/methodology/approach

First, a dynamically buffer allocation model is framed, and buffer zones are given to the activities considering risks. Then, a predictive model amalgamating Bayesian Optimization, Convolutional Neural Networks, and Long Short-Term Memory networks (BO-CNN-LSTM) is framed. Finally, a new buffer monitor framework is constructed that takes into account historical information about buffer usage and utilizes two thresholds derived from control chart theory.

Findings

This approach is empirically tested on a representative agricultural website project in China. The results show that, first, the dynamic buffer allocation makes better use of the project buffer, reduces buffer waste and increases the possibility of timely completion of the project. Second, the BO-CNN-LSTM model predicts better than Long Short-Term Memory (LSTM) and Grey Neural Network Model (GNNM), providing project managers with new management insights and perspectives. Third, the novel monitoring procedure makes the leveraging of historical data possible in the control of the schedule deviations, allowing for more timely interventions in the course of the implementation of the project.

Originality/value

A new project buffer monitoring method suitable for uncertain project environments is proposed.

Details

Kybernetes, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0368-492X

Keywords

Access

Year

Last 3 months (1)

Content type

1 – 1 of 1
Per page
102050