1 – 3 of 3Cenk Budayan, Ozan Okudan and Irem Dikmen
The purpose of this paper is to identify and prioritize key performance indicators (KPIs) that can be used for stage-based performance assessment of build-operate-transfer (BOT…
Abstract
Purpose
The purpose of this paper is to identify and prioritize key performance indicators (KPIs) that can be used for stage-based performance assessment of build-operate-transfer (BOT) projects.
Design/methodology/approach
This research was conducted through focus group discussions and face-to-face questionnaires. Firstly, stage-level KPIs for BOT projects were identified by conducting a literature survey. The list of KPIs that can be used for measuring performance at different stages of a BOT project was finalized by conducting focus group discussions with 12 participants. The data related to the importance of identified KPIs were collected via a face-to-face questionnaire in which 30 high-level managers participated. Based on these data, KPIs were prioritized considering eight different stages of a BOT project by using Technique for Order of Preference by Similarity to Ideal Solution (TOPSIS).
Findings
The research findings reveal that 63 stage-level KPIs can be used for measuring the performance of BOT projects at eight different stages, which are “feasibility study and preliminary plan,” “announcement and submission of application,” “evaluation and selection,” “negotiation and signing of concession agreement,” “design,” “construction,” “operation” and “transfer.” The most important KPIs were determined as “comprehensiveness of project technical feasibility,” “detailed tendering procedure,” “effectiveness of concessionaires' technical knowledge/capability evaluation,” “good relationships between government and concessionaire,” “technology transfer,” “effectiveness of quality control,” “effectiveness of facility management” and “effectiveness of hand-back management” for each stage. The findings can be used by companies to evaluate performance at each stage of a BOT project and, if necessary, take the necessary actions for performance improvement at the stage level.
Research limitations/implications
The main limitation is the size of the sample, which represents the perspectives of 30 Turkish high-level managers on KPIs in BOT projects. Besides, the selected method, namely, TOPSIS, does not provide quality measures related to the outputs; therefore, it is difficult to see the inconsistencies among the experts.
Practical implications
The study findings will help in devising appropriate performance evaluation practices for BOT projects to overcome the shortfalls of the existing practices and systems proposed in the literature and help in achieving the superior performance while developing infrastructure through the BOT route.
Originality/value
This paper proposes a process-based approach for measuring the performance of a BOT project considering eight different stages. It fills a research gap in the public–private partnership literature by focusing on stages rather than phases. The results can be used by practitioners to establish stage-level performance management systems for BOT projects.
Details
Keywords
Ozan Okudan, Cenk Budayan and Irem Dikmen
The purpose of this paper is to develop a new conceptual life cycle performance measurement system (PMS) based on stage level key performance indicators (KPIs) to measure the…
Abstract
Purpose
The purpose of this paper is to develop a new conceptual life cycle performance measurement system (PMS) based on stage level key performance indicators (KPIs) to measure the performance of build–operate–transfer (BOT) projects.
Design/methodology/approach
This study uses a literature review to reveal the deficiencies of existing PMSs for public–private partnership (PPP) projects. Based on these deficiencies, four recommendations were proposed for developing a PMS. The validation of these recommendations was performed via focus group discussion sessions conducted with 12 experts. Then, a conceptual framework was developed based on the validated recommendations and the additional recommendations emerged during focus group discussions. Finally, the recommendations proposed by the focus group were tested by a questionnaire survey, the findings of the Friedman test and descriptive analysis validated these recommendations.
Findings
Findings of the focus group discussion, Friedman test and descriptive analysis indicated that the PMS should have four crucial features to develop an efficient, effective and comprehensible PMS for the BOT project. Firstly, non-financial and financial KPIs should be integrated. Secondly, the PMS should be developed as a process-based system with stage level KPIs. The performance of the BOT projects should be monitored and reviewed continuously, however the most important KPIs should be used for continuous performance measurement to increase the applicability of the system and allocate the resources more efficiently.
Research limitations/implications
This survey was conducted on experts who have experience with BOT projects located in Turkey, therefore, judgments of experts might be affected by external factors specific to Turkey such as geopolitical situations, investment environment. However, due to the nature of BOT projects, the experience of experts can also be utilized at the international level.
Originality/value
This is the first time a PMS has been developed to measure the performance of a BOT project. In addition, this system has unique features when compared with the PMS proposed in the literature. Especially, the stage level KPIs and continuous performance measurement with the most important KPIs throughout each stage has never been used. This research provides both public sector and private entities with an insight into effectively measure, control and manage their BOT infrastructure projects' performances throughout their life cycles.
Details
Keywords
Cenk Budayan, Irem Dikmen and M. Talat Birgonul
The positive effect of differentiation strategy on achieving competitive advantage among construction companies is widely acknowledged in the literature. However, there exists…
Abstract
Purpose
The positive effect of differentiation strategy on achieving competitive advantage among construction companies is widely acknowledged in the literature. However, there exists only a limited number of studies in the construction management literature that investigate the drivers and modes of differentiation. The purpose of this study is to determine appropriate modes and drivers of differentiation strategy in the Turkish construction industry.
Design/methodology/approach
In this study, based on the results of an extensive literature survey, a set of modes and drivers are defined as well as a conceptual framework to investigate their interrelations. Structural equation modelling (SEM) is proposed as an effective tool to investigate the relations between various factors of differentiation and data regarding the Turkish contractors have been used to demonstrate its applicability.
Findings
The results demonstrate that construction companies can differentiate on two modes of differentiation, either on “quality and image” or “product variety and speed”. Among the identified drivers, project management capabilities influence “product variety and speed related differentiation” and “quality and image related differentiation” directly; corporate management affects “quality and image related differentiation” directly, whereas corporate management influences “product variety and speed differentiation” indirectly. “Resources” has a strong direct effect on project and corporate management, in addition “resources” influences “product variety and speed related differentiation” and “quality and image related differentiation” modes indirectly through corporate and project management.
Originality/value
Research findings may help companies to choose an appropriate differentiation mode considering their strengths and weaknesses related with the drivers. Although findings reflect the competitive environment prevailing in the Turkish construction industry, it is believed that the parameters identified in this study can further be used as a benchmark to conduct similar studies in other countries.