To read this content please select one of the options below:

S-curve adjustment approaches for a force majeure event: COVID-19 as an example

Jyh-Bin Yang (Department of Civil Engineering, National Central University, Taoyuan, Taiwan)
Ying-Fu Chen (Department of Civil Engineering, National Central University, Taoyuan, Taiwan)

Engineering, Construction and Architectural Management

ISSN: 0969-9988

Article publication date: 20 October 2023

106

Abstract

Purpose

An S-curve is an essential project-management tool. However, it is difficult to adjust S-curve to deal with a force majeure event. The present study develops four valuable adjustment approaches, designed to achieve a compromise between the views of the client and contractor. These can be used to control projects after a force majeure event.

Design/methodology/approach

The present study develops four adjustment approaches, which can be used to achieve a compromise between the views of the client and those of the contractor when controlling projects after a force majeure. To determine the S-curves during a force majeure event, two approaches can be selected: BCWS (budgeted cost of scheduled work)-base approach, or BCWP (budgeted cost of work performed)-base approach. To determine the rest of S-curves after a force majeure event, two approaches can be considered: maintaining the original curve of the remaining BCWS, or allocating the original curve of the remaining BCWS. Based on the validation of three empirical cases, drawn from a professional project-management website, this study confirms the feasibility of four proposed empirical approaches and a selection procedure for S-curve adjustment.

Findings

The S-curve-adjustment approaches presented here can be used to deal with cases that are ahead of, on and behind schedule. Using the proposed approaches and selection procedure, contractors can easily revise S-curves and control projects more effectively. To deal with a force majeure event, such as COVID-19, they are strongly advised to adopt the approaches labeled SA-A1 (to adjust the S-curve based on the extension ratio multiplied by the difference in progress during the force majeure) and SA-B1 (to maintain the original curve of the remaining BCWS) for the A/E and E/F curves, respectively.

Research limitations/implications

The proposed approaches can be used in cases of continuous construction during force majeure events. If construction work is totally suspended during such an event, it will be necessary to fine-tune the proposed approaches.

Originality/value

Previous studies have used case-oriented or mathematical-simulation approaches to forecast S-curves. The present study proposes simple approaches that allow the client and contractor to adjust the S-curve easily after a force majeure event. These approaches can be used to adjust work and project-completion targets within an extended duration. Selecting the right S-curve adjustment approach can help to control the remainder of the project, reducing the possibility of delay claims.

Keywords

Acknowledgements

The authors would like to thank the National Science and Technology Council, Taiwan, ROC, for financially supporting this research under Contract No. MOST 111-2221-E-008-025-MY3.

Citation

Yang, J.-B. and Chen, Y.-F. (2023), "S-curve adjustment approaches for a force majeure event: COVID-19 as an example", Engineering, Construction and Architectural Management, Vol. ahead-of-print No. ahead-of-print. https://doi.org/10.1108/ECAM-03-2023-0303

Publisher

:

Emerald Publishing Limited

Copyright © 2023, Emerald Publishing Limited

Related articles